IN THE BOMBAY CITY CIVIL COURT AT BOMBAY.
NOTICE OF MOTION NO.3930 OF 2025
IN
L. C. SUIT NO.1598 OF 2025
Mr. Jai Kishen Dhar … PLAINTIFF
Versus
Municipal Corporation of Greater Mumbai and
others.
… DEFENDANTS
APPEARANCES :
Mr. Shobhit Shukla, Advocate for the Plaintiff.
Mrs. Sangita Honmane, Advocate for Defendants/MCGM.
CORAM : AMIT ANANT LAULKAR,
JUDGE
COURT ROOM NO.04
DATED : 01st AUGUST, 2025
ORDER
1.
In instant sequel proceeding, being disgruntled with notice
dated 08.07.2025 issued in pursuance of earlier notice dated
20.04.2024 vide section 351 of the MMC Act, and subsequent speaking
order dated 19.09.2024, the plaintiff herein preferred present suit for
declaration and injunction wherein instant notice of motion was moved
vide Order 39 Rule 1 of the Code of Civil Procedure, 1908.
-- 1 of 7 --
(2)
2.
Per plaintiff, as regards suit property is concerned, they
were cited with notice under section 351 of the MMC Act, followed by
speaking order for demolition thereto. Subsequently, they bounced back
with their reply to the MCGM and eventually, placed their proposal for
regularization of notice structure. Said proposal was placed online with
building proposal department by following all mandatory requisites.
It is urged by the plaintiff that, the building proposal department issued
further particular letter dated 23.10.2024 and returned the
regularization proposal to the architect of the plaintiff. The plaintiff
submits that his proposal for regularization is still pending with AE
(Maintenance) of defendant and thus, it is not rejected with reasoned
orders. The pendency of said proposal is highlighted on the official
portal of defendant/MCGM. The file is displayed and thus, the
regularization proposal is still pending. In the backdrop, issuance of
impugned notice for removal of notice structure is bad in law. On all
these counts, plaintiff knocked the doors of this court with instant suit.
3. As on today, Mr. Shobhit Shukla, learned Advocate for the
plaintiff, submitted that without indulging into merits of the impugned
notice, at the outset, it is to be seen and verified that his/her proposal
for regularization is still pending and in view of ad-interim order passed
in earlier round of litigation, the notice structure is protected. Said
order is annexed with the plaint. On that count, he implored that
regularization proposal is still pending and thus, defendant/MCGM
cannot initiate any action as regard notice structure is concerned.
Eventually, he prayed for ad-interim reliefs in terms of prayer clauses 'b'
and 'c' of the Motion and oblige.
-- 2 of 7 --
Order (3) Notice of Motion No.3930/2025
In L.C. Suit No.1598/2025
4. Post service of notice, defendant MCGM caused appearance
before this Court and tendered short reply cum affidavit along with
documents to oppose ad-interim reliefs. Learned Advocate Mrs. Sangita
Honmane, appearing for the defendant loudly pinpointed letter dated
23.10.2024, addressed to the architect of the plaintiff thereby informing
the rejection of his/her proposal for regularization so also the screen
shot of status-flow of said regularization proposal appearing on the
official portal of the defendant i.e. AutoCAD followed by recent letter
dated 13.06.2025, issued by Executive Engineer (Building Proposal
Department) thereby informing that regularization proposal of the
plaintiff is already rejected and same is uploaded on online AutoDCR
system. Finally, she prayed for rejection of the reliefs in
liminee.
5. Heard both sides. I have pore over entire record minutely.
6. Having considered rival submissions made across the bar, it
is apparent that both parties are in
juxtaposition as regards pendency of
regularization proposal of the plaintiff with defendant/MCGM. To that
effect, upon inquiry, Mr. Pankaj Meher, Sub Engineer, (SE) Building and
Factory Department, M-West Ward, who was present in the court,
clarified that due to non-compliances the regularization proposal moved
by the plaintiff is rejected by Building Proposal Department vide their
order dated 23.10.2024 which is duly communicated to the architect of
the plaintiff. He further highlighted that said proposal is not pending
with building proposal department and to that effect, they have fortified
with their recent letter dated 13.06.2025. Learned Advocate for the
defendant also conceded to the fact that the plaintiff's proposal is duly
rejected long way back for the want of compliances. Barring all
-- 3 of 7 --
(4)
assertions, the letters referred hereinbefore, are also not disputed by the
plaintiff. Those letters categorically suggest the
factum of rejection of
plaintiff's proposal for regularization of notice structure. However, at
the same time, if the winding up lines of the said letter dated
23.10.2024 are scanned minutely then it gives short set back to the
contention of the defendants that the proposal is out-rightly rejected on
all counts. For better understanding those lines are reproduced
hereinbelow
“The proposal submitted with all requisite documents and
compliance will only be considered and process as per its
merits.”
In letter dated 23.10.2024, Building Proposal Department
intimated rejection of the regularization proposal of the plaintiff for the
non compliance of the points detailed in the said letter at Serial Nos.1
to 10. While concluding said letter they quoted aforesaid lines. Those
lines primarily suggest and carried inference that if the plaintiff submit
all requisite documents as detailed in aforesaid letter at Serial Nos.1 to
10 and if, he/she complies then it will be considered and processed as
per its merits. If the proposal is already rejected, then under what
contingency such requisite documents as well as compliances are
expected by the Building Proposal Department, is having shades of
doubt suggestive of nothing but condition for revival of the proposal.
If the proposal is not alive and rejected then it must leave such
impression upon online AutoDCR system, which surprisingly not visible
in instant case in hand. The file for proposal must show finality upon
online AutoDCR system and none would get access furthermore, but it
is not the factual position so far. If the proposal is pending with certain
other departments of the defendant for securing different sanctions,
then it cannot be said that proposal is out-rightly rejected, specially
-- 4 of 7 --
Order (5) Notice of Motion No.3930/2025
In L.C. Suit No.1598/2025
when it gets revived and shows reflection in status flow over online
AutoDCR system.
Thus, having considered entire scenario so also the
recent screen shots of the status of plaintiff's proposal for regularization
derived from official domain of MCGM as displayed and uploaded on
online AutoDCR system annexed herewith the plaint, I believe, there is
no other inference can be drawn than that the proposal is still pending
awaiting for certain compliances to be done by the plaintiff and
eventually evaluated by Building Proposal Department and process it as
per its merits. Aforesaid screen shot of
online AutoDCR system annexed
herewith the plaint, unveils that recently on 19/03/2025 the
documents are submitted to Survey Department and they are awaiting
for survey remarks and approval. This aspects speaks for itself . Be that
it may be, a chance needs to be given to the plaintiff to reveal in what
manner his /her proposal for regularization is still pending or else the
very purpose of the suit as well as of earlier protection would get
infractuous.
7. In such peculiar contingency, especially when the notice
structure is protected in earlier round of litigation till final disposal of
regularization proposal, prima facie, I perceive there is iota of merit in
the version posed by the plaintiff. Without indulging into merits of the
Notice of Motion, on its prima facie evaluation of status of
regularization proposal, the notice structure deserves protection.
Even
there is no separate order passed by the Building Proposal Department
thereby declaring that said proposal is rejected without leaving behind
any off-shoots thereof.
8. Indeed, Pending such proposal, it cast equal duty/
obligation upon the plaintiff or proposer to comply all relevant
-- 5 of 7 --
(6)
formalities along with documentation within stipulated period and act
vigilantly.
9. At the moment, this Court is of the opinion to put time
limits and allied cap's upon the parties for considering the
regularization proposal to which learned Advocate for the defendant/
MCGM fairly agreed and conceded to that effect.
10. As regards, regularization proposal of the plaintiff is
concerned, if any, he/she is directed to submit with all requisite
documents and carry out compliances within Twelve Weeks from the
date of this order. Subject to the filing of all requisite documents and
considering those compliances, the defendants/MCGM shall decide the
same within four weeks thereafter. Till that period, no effect shall be
given to the impugned notice dated 08.07.2025. In the event, result of
the regularization application is adverse to the plaintiff, the impugned
notice and the order impugned in the suit shall not be implemented for
a period of two weeks from the date of decision of regularization
application. Both parties shall place status report of said proposal before
this Court on next date. Deviation, if any, in preceding time frame
would entail adverse action against notice structure, without any
further reference to this court.
11. The Notice of Motion is disposed of in aforesaid terms as
there remains nothing to ponder over further. Both parties to take note
of this order.
(Amit Anant Laulkar)
Judge,
Date : 01.08.2025 City Civil Court, Mumbai.
-- 6 of 7 --
Order (7) Notice of Motion No.3930/2025
In L.C. Suit No.1598/2025
“CERTIFIED TO BE TRUE AND CORRECT COPY OF THE ORIGINAL
SIGNED ORDER.”
02.08.2025 3.45 p.m. Shilpa P. Pawar
Stenographer - Grade IUPLOAD DATE TIME
Name of the Judge (With Court
Room No.)
H. H. Judge Shri. Amit A. Laulkar
Court Room No. 4.
Date of Pronouncement of ORDER 01.08.2025
ORDER signed by P. O. on 02.08.2025
ORDER uploaded on 02.08.2025
-- 7 of 7 --