Full Order Text
Order 1 · 21 Jul 2023 · CNR MHCC010074082018
Order Details: Other Pdf Text: MHCC010074082018 Presented on 21-06-2018 Registered on 21-06-2018 Decided on 21-07-2023 Duration 05 Yrs. 1M IN THE BOMBAY CITY CIVIL COURT AT BOMBAY SUMMONS FOR JUDGMENT NO. 174 OF 2018 IN SUMMARY SUIT NO. 75 OF 2018 M/s. J. K. Infra-Utilities Pvt Ltd ] a Company duly registered under the ] provisions of Indian Companies Act, 1956, ] through it’s Authorized Officer, ] Mr. Rajendra Mane, Accounts Assistant ] Age: years, Occupation:Service, ] having it’s registered Office at: ] Unit No.221, 2nd floor, Swastik Disa ] Corporate Park, Opp. Shreyas Cinema, ] L.B.S. Marg, Ghatkopar (W), ] Mumbai- 400 086. ]...Plaintiff VERSUS M/s. Genesis Resorts Private Ltd. ] 302/B, Kadamgiri Complex, ] Hanuman Road, Ville Parle (E), ] Mumbai-400 057. ]...Defendant -- 1 of 10 -- 2 SJ NO. 174/2018 IN SUM SU NO. 75/18 Appearance : Ld. Adv. Ms. Meenakshi Shinde i/b. L.H.Hingu & Co. for plaintiff. Ld. Adv. Mr. Hitesh Shah for defendant. CORAM : HHJ SHRI K. P. SHRIKHANDE C. R. NO. : 61 DATE : 21/07/2023. O R D E R (Dictated and pronounced in open Court) 1] The plaintiff is a private limited company engaged in the business of providing, installing, testing and commissioning and, handing over the operations related to all the types of plumbing, sanitary and firefighting works. The defendant is a private limited company deals in the business of hotel and restaurants. 2] The defendant company intended to construct a multi-star hotel and was in need of contractors for the purpose of supply and installation of plumbing work at the said site and therefore, it floated the tenders. The plaintiff had submitted its quotation. The defendant company had agreed to give the work order to the plaintiff company and accordingly, the work order was issued on 08/02/2013. As per the said work order, the work of the plaintiff company was to design, supply, install, testing and commissioning the plumbing materials and to work at the said site. Total contract value was fixed at Rs.3,75,00,014/- including all the taxes. The defect liability period was 12 months from the date of completion of the work and retention amount was 5% of the total amount of the work completed and the same was agreed to be paid to the plaintiff company on expiration of the period of the defect liability. -- 2 of 10 -- 3 SJ NO. 174/2018 IN SUM SU NO. 75/18 3] According to the plaintiff company, the defendant gave the letter dated 30/04/2013 to it for making certain minor changes with respect to supply and installation of sewage pump with cutter and, panel for kitchen and accordingly, there were changes in respect of the prices of the materials excluding VAT and service tax. However, other terms remained the same as it were agreed in the work order dated 08/02/2013. Due to changes in specification and scope of the work, datum line of the work entrusted to the plaintiff was mutually extended time to time. 4] According to the plaintiff, as per the work order, the plaintiff commenced the work of supply and installation of the plumbing materials and it raised the various RA Bills and it were duly acknowledged by the defendant. Most of the work was completed in or about August, 2014 and some minor work remained to be done. The defendant failed to make the payments despite repeated request. The defendant made the part payment to the defendant time to time and last amount was received on 15/11/2014. 5] According to the plaintiff, as on 01/02/2015, amount of Rs.75,27,213/- was due and payable by the defendant excluding retention amount. The plaintiff regularly demanded the said amount, but the defendant didn’t make the payment and therefore, the plaintiff had issued several e-mails reminding to make the said payment. Later on after adjusting and calculating actual amount, the amount due found to be Rs.74,32,336/- and due retention amount was Rs.19,37,635/- aggregating to Rs.93,69,971/-. According to the plaintiff, the defendant falsely replied by e-mail making false allegation about pending work. -- 3 of 10 -- 4 SJ NO. 174/2018 IN SUM SU NO. 75/18 6] According to the plaintiff, the documents and built drawings were handed over to the consultant of the defendant i.e. to the Nat Engineering Consultant on 23/11/2015 and it is the date of handing over the completed entire project to the defendant. Though the entire project was handed over to the defendant, the defendant didn’t make the payments to the plaintiff. On the other hand, the defendant raised the debit notes upon the plaintiff claiming the amount for which the plaintiff is not liable to pay, only with the intention to delay and defeat the legitimate claim of outstanding amount of the plaintiff. According to the plaintiff, the defendant is liable to make the payment of Rs.74,32,336/- towards the outstanding amount and amount of Rs.19,37,635 as retention amount aggregating to Rs.93,69,971/-. 7] On appearance of the defendant, the plaintiff served on the defendant the summons for judgment, and the defendant then filed the affidavit in reply to the summons for judgment praying to grant leave to defend the suit. 8] Counsel for the plaintiff submits that the defendant has raised the moonshine defence and in fact, there is no defence of the defendant. According to him, no triable issues have been raised by the defendant and the defendant is not even entitled to the conditional leave, and prayed for granting leave to sign the judgment. The defendant and his counsel are absent. Record and the Roznama shows that they were also absent on the previous dates and therefore, taking into consideration the submission of counsel for the plaintiff and going through the reply of the defendant filed to the summons for judgment, I proceed to decide whether the plaintiff is entitled to sign the judgment or whether the defendant is entitled to leave to defend the -- 4 of 10 -- 5 SJ NO. 174/2018 IN SUM SU NO. 75/18 suit. 9] It is apparent that the defendant has not disputed about giving the work order dated 08/02/2013. It is apparent that various terms and conditions have been included in the said work order and in accordance with the said terms and conditions, the work was to be executed. The said project undisputedly was to be completed by 30/06/2013. However, according to the plaintiff, it has been completed and handed over to the defendant on 23/11/2015. It is seen that the defendant has denied of extension of the time-limit of completion of the project. 10] There is no dispute that plumbing and sanitation work was to be carried out for the amount of Rs.2,61,54,169.34 and firefighting and sprinkler was for the amount of Rs.1,13,45,844.95 aggregating to Rs.3,13,45,844.95. It is apparent that it was the estimate cost of the project and was not the fixed cost. It is clearly mentioned in the work order that “this is an Indivisible Works Contract which is an item rate contract and not a lump-sum work. Quantities mentioned in the said schedule of the qualities are approximate and are subject to variation by addition, reduction, omission or deletion. 11] RA bill was to be raised on monthly basis and the defendant had agreed to pay the amount. However, as per the contention raised by the defendant, the said RA bill was to be raised and approved by project manager/valuation engineer/Nat Engineering Consultant; however, RA bills submitted by the plaintiff were not approved by project manager/valuation engineer/Nat Engineering Consultant. According to the defendant, RA bills submitted were the tentative RA bills. Though the plaintiff has placed on record the RA -- 5 of 10 -- 6 SJ NO. 174/2018 IN SUM SU NO. 75/18 bills, it is not appearing that it were either approved by the project manager, or valuation engineer, or Nat Engineering Consultant. So the exact liability of the defendant to pay the amount on the basis of those RA bills is questionable though the defendant has paid many times the amount towards the work done by the plaintiff. 12] As per the contention raised by the defendant, the plaintiff to had to file two different suits based on the 1st and 2nd work orders and raised the question on the maintainability of a single suit. According to it, work order dated 08/02/2013 and work order dated 30/04/2013 are altogether different; however, the plaintiff has raised the RA bills in continuation of both the projects as if both the work orders were in respect of the same work/project. After going through those work orders, it is appearing that in both the work orders, terms and conditions have been described with the clarity. In the 2nd work order, work/project was to be completed by 15/07/2013. It is not pointed out by the counsel for the plaintiff that 2nd work order has a reference of the previous i.e. 1st work order dated 08/02/2013. Therefore, prima-facie there are sufficient reasons to believe the defendant that 1st work order and 2nd work order are different. The plaintiff has raised the common RA bills as if the both the projects were one and the same. So, it is also the triable issue whether the plaintiff ought to have filed two different suits relating to the two work orders and whether the present single suit is maintainable. 13] There is no dispute that the plaintiff had made demand of the outstanding amount several times by issuing the e-mails. It is also appearing that the defendant had replied the e-mail and denied the liability to pay the outstanding amount by raising the grievances that the project is not completed and handed over and certain works are -- 6 of 10 -- 7 SJ NO. 174/2018 IN SUM SU NO. 75/18 incomplete. It is appearing that the RA bills were to be raised with reference to the various terms and conditions depending on the quality and quantity of the materials used. The defendant has raised the dispute about carrying out the complete work and handing over the project. RA bills are not appearing to have been approved by the certified person/expert mentioned in the work order. So, the contention raised by the defendant that the suit is not for the liquidated amount as the balance amount was not finalized, cannot be said to be without any substance and thus, substantial defence of maintainability of the suit has been raised and it can be said that the defendant has raised the triable issue of maintainability of the summary suit. 14] The defendant has raised the point of using the sub- standard materials and not doing the work as per the terms and conditions. Whether the work has been carried out as per the terms and condition is also a triable issue in order to fix the liability of the defendant for the particular quantum of amount. So, another question arises whether the suit filed by the plaintiff is for the liquidated amount, and certainly it is the triable issue as it also goes to the root of maintainability of the summary suit. 15] It is also the contention of the defendant that the suit is not filed within the period of limitation. It is appearing that both the work orders had the different date for completion of the project. As per the contention raised by the defendant, the project is not completed by the date fixed and not handed over. As per the contention raised by the defendant, the suit is not filed within the period of limitation. Undisputedly, the last payment of Rs.4,00,000/- was made on 15/11/2014. Suit is filed on 21/11/2017. Therefore, it -- 7 of 10 -- 8 SJ NO. 174/2018 IN SUM SU NO. 75/18 can be said that the defendant has raised probable defence and raised the triable issue about not filing the suit within the period of limitation. 16] Therefore, having regard to the various points raised by the defendant in the reply/leave to defend the suit, I’m of the view that the defendant has raised the substantial defence and raised the triable issues and as such, the defendant is entitled for the leave to defend the suit unconditionally. Merely because of failure of the defendant to argue on the entitlement of the plaintiff to sign the judgment and on the point of granting the leave to defend the suit, it cannot be held that the plaintiff has become ipso-facto entitled to sign the judgment. In the result, I proceed to pass the following order. O R D E R 1] Summons for judgment No.174 of 2018 is dismissed. 2] Leave to defend the suit is granted unconditionally. 3] The defendant to file the written statement within 6 weeks. 4] Summons for judgment No.174 of 2018 is disposed of. Mumbai (K. P. Shrikhande) Date: 21/07/2023 Judge, City Civil Court Gr. Mumbai. Court Room No.61 Dictated on: 21-07-2023 Corrected & signed on: 26-07-2023 -- 8 of 10 -- 9 SJ NO. 174/2018 IN SUM SU NO. 75/18 CERTIFIED TO BE TRUE AND CORRECT COPY OF THE ORIGINAL SIGNED JUDGMENT/ORDER” UPLOAD DATE AND TIME NAME OF STENOGRAPHER 26-07-2023 at 4.00p.m. Mrs. V. V. Malgaonkar Name of the Judge (with Court Room No.) Shri K. P. Shrikhande C.R. No.61 Date of Pronouncement of JUDGMENT/ ORDER 21-07-2023 JUDGMENT/ORDER signed by P. O. on 26-07-2023 JUDGMENT/ORDER uploaded on 26-07-2023 -- 9 of 10 -- 10 SJ NO. 174/2018 IN SUM SU NO. 75/18 -- 10 of 10 --
