Full Order Text
Final Order 1 · 05 Aug 2019 · CNR MHCC010062302019
Order Details: Notice of Motion Pdf Text: 1 IN THE COURT OF CITY CIVIL COURT AT GR.BOMBAY NOTICE OF MOTION NO.2268 OF 2019 IN COMMERCIAL S.C. SUIT NO.27 OF 2019 CNR NO.MHCCO10062302019 Shree Anukul Industries Pvt.Ltd } Having address at 51/52, Shubh } Commercial premises, Akruli Rd, } Opp. ESIS hospital, Kandivali(E) } 400 101. } ..Plaintiff V/s 1. Maharashtra Jeevan } Pradhikaran } Having address at 4th floor, } Express Tower, } Nariman Point, Mumbai } 2. Karnataka Bank Ltd } Having address at LIC Complex } J.B.Nagar, Borivali West. } 400 103 } ..Defendants Ld. advocate Bernardo Reis with adv.Viraj Kandpile for plaintiff Ld. advocate Ajit Pitale for defendant no.1 Ld. advocate S.R.Shetty for defendant no.2 CORAM: HIS HONOUR JUDGE SHRI M.SALMAN AZMI DATE: 05/08/2019 ORAL ORDER 1. This Notice of Motion is tendered by the plaintiff company interalia for restraining defendants from acting upon the letter of termination dated -- 1 of 16 -- 2 16/04/2019 and letter for encashment of bank guarantee and further restraining the defendants from assigning the work to any third party which was assigned to the plaintiff company vide work order dated 17/06/2017. 2. Heard. 3. In short the contentions of the plaintiff company was that the plaintiff company was lowest financial bidder for the work of augmentation to Nhava Sheva water supply scheme, stage III. The work order was issued on 17/06/2017 to the plaintiff company. The plaintiff company has submitted bank guarantee of Rs.68,44,404/. The defendant no.1 delayed by over 7 months for approving alignment under the said work order as well as delay in site clearances for implementation of the project. The costs of execution of works under the said work order was 40% increased. It was agreed that plaintiff company will be compensated for the actual tax difference arising due to GST after taking into account input tax credit excluding input tax credit of excise exempted items like MS pipes, coating valves etc. Defendant no.1 falsely stated to impose penalty charges on account of delay in execution of the work. The delay cannot be attributed to the plaintiff company. The considerable time for a period of four months was lost due to the monsoon. Moreover, plaintiff company stated that land owners where site -- 2 of 16 -- 3 clearance were handed over were not allowing them to execute works under the said work order. Plaintiff company by letter dated 27/01/2018 gave defendant no.1 a detailed account of the ground reality of the financial burden imposed upon them due to GST. By letter dated 14/06/2018, plaintiff company recorded the financial burden of this project as imposed upon them and stated that the costs for MS plates, diesel, cement etc have an average increase of 41.14%. Defendant no.1 was never interested in project completion. The plaintiff company had burden of excise duty and GST of Rs.77 lacs. Defendant no.1 had no intention of refunding the amount of Rs.77 lacs incurred by the plaintiff company. Defendant no.1 has no authority to terminate the said work order since plaintiff company has completed approximately 40% of the said work and cannot be terminated without following due process. The said notice of termination dated 16/04/2019 is illegal and bad in law. The plaintiff company apprehends of encashment of bank guarantee, therefore the plaintiff company was compelled to file the present suit alongwith accompanying notice of motion. 4. The defendant no.1 resisted the claim of the plaintiff company by filing the reply and the written statement. It is the contention of defendant no.1 that it is a ambitious National importance scheme of supply of drinking water to Jawaharlal Nehru Port -- 3 of 16 -- 4 trust and also to cater the potable water demand of Panvel Municipal Corporation and CIDCO area and also to cater the water demand of 19 surrounding villages. By work order dated 17/06/2017 the contract to plaintiff company was supposed to complete the work within 18 months i.e. by 16/12/2018. The plaintiff company has only completed 40% of the work by the end of December 2018. Defendant no.1 issued number of letters and reminders to plaintiff company requesting to complete the work within stipulated time, but the plaintiff company ignored all the instructions and the conditions of tender. Therefore, defendant no.1 has imposed the penalty in conformity with the notifications and guidelines. The penalty imposed by the defendant no.1 has reached to the extent of Rs.3,14,19,223/ as on 15/04/2019 and for recovery of the said penalty amount, defendant no.1 is proposing to encash bank guarantee of Rs.68,44,404/. As per the request of the plaintiff company, defendant no.2 extended the bank guarantee upto 31/05/2019. As per clause 3(c) of the tender the contract was terminated. There is no cause of action for filing suit. Hence, prayed for rejection of the notice of motion. 5. On the rival submissions of the parties, following points arise for my determination and findings to it are recorded for the reasons stated to follow: -- 4 of 16 -- 5 POINTS (i) Whether the plaintiff company has made out a prima facie case? (ii) Whether the balance of convenience lies in favour of plaintiff company? (iii) To whom the irreparable loss would be caused? (iv) What order? FINDINGS (i) In the negative. (ii) In the negative. (iii) To the defendants. (iv) As per final order REASONS POINT NOS.1 TO 3 6. The parties are not at dispute that work was assigned to the plaintiff company as plaintiff company was the lowest bidder in the financial bid in the StageIII, Nhava Sheva water supply scheme. The work order was issued on 17/06/2017 and thereby it was directed to the plaintiff company to complete the work within 18 months (during monsoon) from 17/06/2017. The plaintiff company was called upon to furnish bank guarantee of Rs.68,44,404/. The contract of the plaintiff company was terminated for the said project by termination letter dated 16/04/2019. Defendant no.1 wrote to defendant -- 5 of 16 -- 6 no.2 vide letter dated 17/05/2019 for encashment of the bank guarantee. The contention of the plaintiff company is that defendant no.1 has played fraud upon the plaintiff company. The plaintiff company was forced to incur Excise duty and GST amounting to Rs.67 lacs and Rs.10 lacs on all costs incurred by the plaintiff company for execution of the work which was not the part of the contract. Defendant No.1 denies the said contention. The advocate for plaintiff company pointed out that there is Excise duty exemption clause in the tender. The relevant clause is reproduced as under: “The concession would be subject to the certification by the collector/District Magistrate/Deputy Executive Engineer of the District in which the water treatment plant is to be setup. To avail exemption on duty the tenderer himself shall pursue the matter with different Government Departments. Any cooperation in this regard will be extended to the tenderer. The tenderer shall quote his offer taking into account above exemption which he may avail.” 7. The Ld. Counsel for defendant no.1 pointed out that plaintiff company has submitted various bills in respect of the purchase of the pipe lines, coating, valves etc which are exempted from Excise duty. He would submit that on 01/07/2017, The Goods and Services Act was enacted. Upon the request of the -- 6 of 16 -- 7 plaintiff company, meeting was conveyed at JNPT office, Raheja Chambers, Nariman Point, Mumbai on 25/07/2017 with the agenda of discussing Excise Duty reimbursement & GST under the said works order. The meeting was attended by the Chairman of JNPT, Member Secretary of defendant no.1 as well as many others, where it was agreed that contractor would be compensated for the actual tax difference amount arose due to GST after taking into account the input tax credit excluding input tax credit of Excise exempted items like MS pipes, coating, valves, MS specials etc. The plaintiff company vide letter dated 27/07/2017 demanded the minutes of meeting dated 25/07/2017 and requested defendant no.1 to confirm the minutes of the meeting dated 25/07/2017 so that actual work would be started. The bone of contention of the plaintiff company is that there was unavoidable reasons for delay in execution of the work. The fact that progress of work was subject to timely Excise exemption, site clearance and condition. The plaintiff stated that pipe fabrication factory was flooded on account of monsoons and it was practically impossible to begin excavation work during the monsoon period. On the other hand it was the stand of defendant no.1 that previous letters and reminders were issued to the plaintiff company to carry out the work at the earliest. The letter dated 28/09/2017 by defendant -- 7 of 16 -- 8 no.1 to the plaintiff company reflects that the work was not as per work schedule submitted by the plaintiff company and the plaintiff company was called upon to carry out the work as per the time schedule given by the plaintiff. The letter dated 18/12/2017 was again issued. The representation was made to the plaintiff company that work is unsatisfactory and he was called upon to submit the report to defendant no.1 as to how he would complete the work within the time schedule in the tender. The plaintiff company responded to the said letter by reply dated 23/12/2017. He made the contentions that minutes of the meeting dated 25/07/2017 were issued to them on 25/10/2017 after a period of three months. The plaintiff company had applied for QAP approval of pipes vide letter dated 21/08/2017, however they received QAP approval after a period of one month i.e. on 21/09/2017. He also raised issue that due to monsoon excavation work was not started and there were resistance from the villager due to which the work was stopped. Again the letter dated 19/01/2018 was issued to the plaintiff. It was expected that 39% of the work should have been completed. In respect of GST and Excise that the plaintiff company was called upon to submit the calculation sheet and the same is required to be approved from the Finance Department and to -- 8 of 16 -- 9 complete the work within the time period. The plaintiff company by letter dated 27/01/2018 informed defendant no.1 and expressed its inability to carry out the work as the work has been stopped by concerned road contractor for almost a period of nine months and after due persuasion they were asked to shift the alignment for pipe laying at a distance of 40 meters from road center. The defendant no.1 by letter dated 15/02/2018 informed the plaintiff company that expected 44% of the work has not been completed and was called upon the plaintiff company to complete the work. By letter dated 20/08/2018, the plaintiff company was again informed by defendant no.1 that 60% of the work was supposed to be completed and it appears that the work would not be completed within a period of four months and if the work is not completed the penalty would be imposed. On 30/08/2018, the letter was issued by defendant no.1 to plaintiff company and called upon to give the schedule as to how plaintiff company would complete the work within a short span of time. Again by letter dated 14/02/2019, the plaintiff company was called upon to complete the work and so far as the issue regarding GST, plaintiff company was informed that same is pending before the Government for its decision. Thereafter again plaintiff company was called upon by defendant no.1 on 16/02/2019 to -- 9 of 16 -- 10 complete the work. By letter dated 02/03/2019, the plaintiff was informed as regard the meeting dated 28/02/2019 and various issues were discussed in the said meeting and accordingly the plaintiff company was informed about the same. Ultimately on 16/04/2019, the contract was terminated. 8. It is apparent that there were several correspondences from defendant no.1 to the plaintiff company for timely completion of the work. although the plaintiff company has replied and showed its inability in the progress of the work. The issue that factory was flooded in monsoon cannot be the ground because the time limit includes the monsoon season and plaintiff company was well aware about the same. So far as the issue of Excise and GST exemption is concerned, it is nowhere coming forward that defendant no.1 has denied for the same. But for the GST it was made clear that decision is pending at the Government level. The other issue of escalation of price claimed by the plaintiff company, it was made clear that the plaintiff company was not entitled for the same and therefore it was not considered. Even otherwise the plaintiff company has given understanding that plaintiff company will not claim escalation. 9. At this juncture, the issue which is relevant is whether the defendant no.1 can encash the bank guarantee. The argument of the plaintiff company is -- 10 of 16 -- 11 that the termination is illegal. The clause (3) of the agreement contemplates that if any case in which under any clause of this contract the contractor shall have rendered himself liable to pay compensation amounting to the whole of his security deposit (whether paid in one sum or deducted by installment) or in the case of abandonment of the work owing to serious illness or death of the contractor or any other cause, the Executive Engineer on behalf of the MJP shall have power to adopt any of the courses, as he may deem best suited to the interest of the MJP. It is the contention that as per clause (c) the contract was terminated. It is argued on behalf of defendant no.1 that the work was not completed by the plaintiff company within stipulated time. Only 40% of the work has been completed. Therefore the contract was terminated. The clause (3) is clear that defendant no.1 has a right to deduct the excess from any money due to the contractor under the contract or otherwise however or from his security deposit or the sale proceeds thereof in case of the costs of the execution through the new contractor and exceeds the certified cost of such work and allied expenses. Thus the guarantee was a performance guarantee. The contention of the plaintiff company is that it is a additional security is not apparent from the terms of tender. There are rival contentions for delay in -- 11 of 16 -- 12 execution of the work. But, at this juncture this is disputed question of facts which needs to be considered after the scrutiny of the evidence. It would not be proper for this Court to come to conclusion at the time of deciding interim application that the contract was validly terminated. One thing which this Court cannot ignore is that time and again written instructions were given to the plaintiff to complete the work within the time period considering the nature of project. This fact is relevant at the time of deciding this notice of motion. 10. The issue of GST to the tune of Rs.77 lacs is before the Government for the consideration as argued by defendant no.1. It is settled position of the law that injunction cannot be granted for restraining from invocation of the bank guarantee unless the fraud is pointed out. The fraud should be such that it would vitiate entire transaction and it is irretrievable injustice or irreparable harm. Merely the fact that bank guarantee has been extended cannot be the ground for grant of injunction. 11. Ld. Counsel for the plaintiff placed reliance upon the following judgments: Hindustan Steelworks Construction Limited V/s Tarapore & Co and another of Hon'ble Apex Court (1996) 5 Supreme Court Cases 34 U.P.Cooperative Federation Ltd V/s Singh Consultants and Engineers (P) Ltd of Hon'ble Apex Court (1988)1 Supreme Court Cases 174 -- 12 of 16 -- 13 There is no quarrel about the law laid down by the Hon'ble Supreme Court in above cited cases. It has been held by the Hon'ble Supreme Court that, injunction restraining the encashment of bank guarantee can be granted only in case of fraud or in case of irreparable loss. No such contingency has been pointed out. 12. At the very outset company would have made clear that till the issue of GST is resolved, plaintiff company would not have proceeded with the execution of work. The issue of payment of the amount towards the GST cannot be attributed as fraud upon defendant no.1. The payment of GST liability is outcome of the subsequent Legislation enacted and therefore it cannot be said that defendant no.1 has played fraud upon plaintiff company. Even otherwise the plaintiff company is coming with the case that efforts were made by defendant no.1 to resolve the same. It is apparent that there is nothing on record to prima facie show that any fraud has been committed by defendant no.1 and therefore defendant no.1 cannot be prevented from invoking the bank guarantee at this stage. 13. By this notice of motion plaintiff company prays that defendant no.1 be restrained from acting upon the termination letter dated 16/04/2019. As discussed above it would not be proper to examine -- 13 of 16 -- 14 the validity of the termination letter at the interim stage. The notice was issued on 16/04/2019, plaintiff knocks the door of the Court challenging its validity after one and half months. The delay in approaching the Court cannot be given go bye. Even otherwise at this stage it cannot be overlooked that the work is pertaining to augmentation to Nhava Sheva water supply scheme and same cannot be kept in abeyance pending the disposal of the suit. Therefore, at this stage the other prayer of the plaintiff for restraining defendant no.1 from creating third party interest in respect of work order issued in favour of plaintiff also cannot be considered. If the work is withheld it will frustrate the project which is meant to supply drinking water to JNPT, and carter the water demand of Panvel Municipal Council and others. In that event the project cost will increase and thus would cause irreparable loss to defendant no.1. In view of the above matter, this notice of motion needs no consideration. Hence, I am compelled to answer point nos.1 to 3 in the negative. POINT NO.4 14. In view of the above discussion, the Notice of Motion deserves to be rejected. Accordingly, it is expedient to pass following order: ORDER 1. Notice of Motion No.2268/2019 is rejected. -- 14 of 16 -- 15 2. Costs in cause 3. Notice of Motion is disposed of accordingly. 05/08/2019 M.SALMAN AZMI CITY CIVIL COURT, GR.MUMBAI. Dictated on : 05/08/2019 Transcribed on : 06/08/2019 Signed on : 08/08/2019 'CERTIFIED TO BE TRUE AND CORRECT COPY OF THE ORIGINAL SIGNED JUDGMENT/ORDER”. 08/08/19 at 6.00 pm. MRS.T.C.KAMBLE Name of the Judge HHJ SHRI M.S.AZMI, CR NO.16 Date of Pronouncement of judgment/order 05/08/2019 Judgment and order signed by P.O. 08/08/2019 Judgment/order uploaded on 08/08/2019 -- 15 of 16 -- 16 -- 16 of 16 --
