Full Order Text
Final Order 1 · 30 Aug 2021 · CNR MHCC010045912019
Order Details: Chamber summons Pdf Text: CS 897 of 2019 in Suit No. 2104 of 2014 1 Dt. 30/08/2021 IN THE BOMBAY CITY CIVIL COURT AT BOMBAY CHAMBER SUMMONS NO. 897 OF 2019 IN SUIT NO. 2104 OF 2014 CNR NO. MHCC010045912019 Mr. Nitin Kantilal Gandhi ...Plaintiff. V/s. Srushti Raj Enterprises (India) Ltd. ...Defendant And Hemlata Dinesh Mali & Ors. ...Respondents APPEARANCES: Ld. Adv. Gargi Bhagwat for plaintiff. CORAM : HHJ SHRI A.H.LADDHAD DATE : 30/08/2021 (C.R.NO.3) ORDER 1. The plaintiff has filed instant Chamber Summons with following reliefs : (a) That the delay, if any, in taking out the present Chamber Summons be condoned. (b) This Hon'ble Court be pleased to permit the plaintiff to amend the plaint in terms of schedule annexed hereto. (c) Pending the hearing and final disposal of this Chamber Summons, the respondents or its servants, agents, or any other person claiming through them be restrained by a temporary order and injunction of this Hon'ble Court -- 1 of 4 -- CS 897 of 2019 in Suit No. 2104 of 2014 2 Dt. 30/08/2021 hereto from in any manner dealing with, disposing of selling, transferring, alienating, encumbering or parting with the possession of the flat being Flat No. 604, admeasuring about 760 sq. ft. carpet area on the 6th floor in the "B" Wing of the building tentatively named "Srushti Raj Towers" situated at Plot No. 103, 13th Road, Tilak Nagar, Chembur, Mumbai 400 089 alongwith one stilt parking space. (d) Cost of the present Chamber Summons be provided for. (e) Such further and other reliefs as this Hon'ble Court may deem fit and proper in the facts and circumstances of the present case. 2. It is the contention of the plaintiff that inspite of pendency of the suit, the defendant no. 1 created third party interest with respect to suit property. Therefore, the plaintiff wanted to place the subsequent development on record. Therefore, he prayed for allowing Chamber Summons. 3. The respondents although served but, failed to appeared. The suit is already proceeded exparte against them. I have heard Ld. Advocate for the plaintiff. Perused Chamber Summons and Affidavit. The plaintiff filed present suit for specific performance of the contract with respect to suit property. During pendency, my Predecessor vide, order dated 28.07.2017 granted adinterim relief in terms of prayer clause (a), thereby restrained the defendant from transferring the suit property. As per the contention of the -- 2 of 4 -- CS 897 of 2019 in Suit No. 2104 of 2014 3 Dt. 30/08/2021 plaintiff, he learned that the defendant on 09.03.2017 executed Sale Deed of suit flat with Dinesh Mali and Hemlata Dinesh Mali. Therefore, the plaintiff prayed for adding his name as necessary party. The plaintiff by way of proposed amendment, does not seek any other relief which could change the nature of the suit. The aforesaid amendment is necessary to adjudicate the lis between the party. Hence, I am of the view that Chamber Summons needs to be allowed. Thus, I proceed to pass the following order : ORDER 1. The Chamber Summons No. 897 of 2019 is hereby allowed in terms of prayer clause (a) and (b). 2. Plaintiff to carry out necessary amendments within a period of 14 days from the date of order. 3. Chamber Summons No. 897 of 2019 stands disposed of accordingly. (A.H.LADDHAD) DATE: 30/08/2021 ADDITIONAL SESSIONS JUDGE GRATER MUMBAI Dictated on : 30/08/2021 Transcribed on : 30/08/2021 Draft submitted on : 30/08/2021 Checked on : 31/08/2021 Signed on : 31/08/2021 -- 3 of 4 -- CS 897 of 2019 in Suit No. 2104 of 2014 4 Dt. 30/08/2021 “CERTIFIED TO BE TRUE AND CORRECT COPY OF THE ORIGINAL SIGNED JUDGMENT/ORDER.” 31/08/2021 at 4.00 p.m. (Ms. V. V. Sawant) UPLOAD DATE AND TIME NAME OF STENOGRAPHER Name of the Judge (With Court room no.) Shri A.H.LADDHAD (C.R. No.3) Date of Pronouncement of JUDGMENT/ ORDER 30/08/2021 JUDGMENT/ORDER signed by P.O. on 31/08/2021 JUDGMENT/ORDER uploaded on 31/08/2021 -- 4 of 4 --