Full Order Text
Order 1 · 25 Apr 2018 · CNR MHCC010034112018
Order Details: Notice of Motion Pdf Text: 1 NM no 1052-18 STAM no. 3767-2018 CNR MHCC010034112018 IN THE CITY CIVIL COURT FOR GREATER BOMBAY AT BOMBAY. NOTICE OF MOTION NO.1052 OF 2018 IN STAMP NO.3767 OF 2018 Yogesh Construction Private Limited ]..Plaintiff Versus Municipal Corporation of Gr. Mumbai ] & 3 Ors. ]... Defendants Coram : M.S. Deshpande, Judge (Court Room no. 05) Date : 25th April, 2018. Mr.Uday Shankar Samudrala, advocate for plaintiff. Mr. Mhatre, advocate for defendant nos.1 to 3. M.G. Rane, Manager of defendant no.4. ORDER 1. Heard respective advocates at length. The learned advocate for the plaintiff submitted that on work contract for providing and laying various sewer works lying at various places, three Bank guarantees for security deposit and retention money were given in 2011. The said Bank guarantees were subject matter of accounts between the plaintiff and the defendants upon finalization of the bills. According to him, the plaintiff is entitled for an amount of Rs.30 lakhs to 40 lakhs to be recovered from the defendant. However, in spite of the completion of the work, the defendants did not prepare final bills and they sought extension of the bank guarantees from time to time for last four years. According to him, the work is also handed over. He further submitted that the defendants illegally encashed one of the -- 1 of 5 -- 2 NM no 1052-18 STAM no. 3767-2018 three bank guarantees. He submitted that the bank guarantees could be encashed only if some amount is to be recovered from the plaintiff. However, here the defendant Corporation has to finalize the bill and pay the amount of the work carried out to the plaintiff. He has placed reliance on the ratio laid down by the Hon'ble Supreme Court in Hindustan Construction Co. Ltd. vs. The State of Bihar & Ors. to the effect that the terms of Bank guarantee are extremely material and therefore, amount covered by the guarantee is payable only if obligations under contract are not fulfilled by the contractor or there is misappropriations. It is also held that the invocation of bank guarantee will have to be in accordance with the terms of bank guarantee. 2. On the other hand, the learned advocate for the defendant nos.1 to 3 (for short, “the defendants”) submitted that as per the general conditions of contract, clause no.96 in case of dispute / claim by other party, the aggrieved party should refer the same to Assistant Municipal Commissioner and the A.M.C. should constitute a committee which shall give a decision. There is provision for appeal to Municipal Commissioner against such decision and his decision would be final. He further submitted that considering the provision of appeal the plaint should be returned to the plaintiff. The plaintiff is trying to prevent the defendant from executing the terms and conditions of the contract. 3. He further submitted that the plaintiff has not properly carried out the work under contract and is also not ready to carry out rectification work, and therefore, the remaining work was required to be given to other agency and therefore, final bill was not prepared. According to him, for such reasons the security deposit and retention money kept in the form of Bank guarantees are required to be enforced. -- 2 of 5 -- 3 NM no 1052-18 STAM no. 3767-2018 4. Prima facie, it is undisputed that the defendant has encashed the Bank guarantee dated 4.11.2011 for Rs.2,08,200/ which was given towards security for refund of retention money. There are two other Bank guarantees for Rs.10,03,000/ and Rs.13,76,026/ issued towards contract and security deposits and for security for refund of retention money etc. Prima facie, it is undisputed that the bank guarantees were required to be kept in force till finalization of the account and payment of final bill. The total costs for the work under contract was Rs.5,25,60,760/ and the work was to be completed within stipulated time. The validity of the remaining two bank guarantees was extended till 13.4.2018. 5. The plaintiff has filed suit for declaration that the defendant no.3 is not entitled to encash any of the bank guarantees on the pretext that validity of the bank guarantee is/ was not extended by the plaintiff and further for a consequential relief of injunction for restraining the defendants from encashing remaining two bank guarantees. The scope of the suit is very limited. 6. It prima facie appears, on 3.10.2007 the tender given by the plaintiff was accepted by the defendants with request to commence the work from 25.10.2007 and complete the same within 15 months exclusive of monsoon period. It was also given under general conditions of contract for civil works that if the bank guarantee is not renewed within 7 days before the expiry of validity period, it will be encashed, and that security deposit, retention money, performance guarantee shall be refunded to the contractor only on finalization of final bill, settlement of accounts of the work by the contractor in all respect or after completion of defect liability period whichever is later. -- 3 of 5 -- 4 NM no 1052-18 STAM no. 3767-2018 7. Prima facie it appears that on 22.9.2017, the defendants issued show cause notice under clause 90(a) of General conditions of Contract calling upon the plaintiff to explain the reasons for not fixing C.I.F. frame covers for manholes, cleaning, removing of debris etc. in respect of the various sites. It also appears that there are allegations against each other through cross correspondence and such details are required to be considered on merits. However, it prima facie appears that the plaintiff has not observed the basic conditions i.e. renewal of bank guarantees and further referring the aforesaid dispute to the Assistant Municipal Commissioner as contemplated under the general conditions of contract for Civil work. Undisputedly, the accounts were not settled and final bills were not prepared. Therefore, intervention of this Court is not warranted at adinterim stage. Therefore, the following order is passed: ORDER 1. Adinterim relief is rejected. 2. As there was order of statusquo granted earlier, in terms of the same, so as to facilitate the plaintiff to approach the Hon'ble High Court, the order of statusquo is continued till 03.5.2018 with a direction that it will not be extended on any count. 3. An ordinary copy of this order duly authenticated by the Sheristedar of this Court be supplied to respective parties. Sd/- (M.S. Deshpande) Ad hoc Judge, City Civil Court, Mumbai. Directly typed on : 25/04/2018. Checked by HHJ on : 25/04/2018. Signed by HHJ on : 25/04/2018. -- 4 of 5 -- 5 NM no 1052-18 STAM no. 3767-2018 “CERTIFIED TO BE TRUE AND CORRECT COPY OF THE ORIGINAL SIG JUDGMENT/ORDER.” UPLOAD DATE AND TIME : 27.04.2018 At 11.16 a.m. NAME OF STENOGRAPHER : Mrs. V. U. Pawar Name of the Judge (With Court Room no.) HHJ Shri. M. S. Deshpande C.R. no.05 Date of Pronouncement of JUDGMENT/ORDER 25.04.2018 JUDGMENT/ORDER signed by P.O. on 25.04.2018 JUDGMENT/ORDER uploaded on 27.04.2018 -- 5 of 5 --
