Skip to main content
DELAY CONDONATION APPL

M/s. Decent Soap Factory Pvt. Ltd. in Misc. Appeal St. No.2824 of 19VsMCGM

CNR MHCC0100262120194-COURT 04 ADDL SESSIONS JUDGE
City Civil Court, Mumbai
Mumbai · Maharashtra (MH)
CASE DISPOSED
Uncontested--OTHERWISE
Decision Date: 13th March 2019

TrustJury record updated 19 Sept 2026

Case Overview

Registration Number
100068/2019
Registration Date
07 Mar 2019

Advocates

1

For Petitioner

For Respondent

    Not available

    Parties

    2

    Acts & Sections

    1
    Terrorist and Disruptive and Activities (Prevention) Act · Sec 105F

    Case History / Proceedings

    Case History
    Date: 13-03-2019
    Business: Adv. D.A. Thorat for appellant present.
    Adv. for respondent present.
    Heard the Ld. adv. for appellant as well as  the Ld. adv. for respondent. The Ld. adv. for respondent has submitted that sufficient opportunity has been given and the delay has not been explained. I have examine the submissions of the parties. The delay does not to be appeared inordinate. Only 5 days delays is there. With a view that the appellant may be heard on merits, the delay may be condoned.  Hence, the delay occurred filed is appeal is condoned on the appellant paying cost of Rs. 1,000/- to  the DLSA. Mumbai. In these terms, the application for delay stands disposed off.
    Appeal be registered and be placed before the court for hearing the parties on ad-interim relief.
    Matter is adjd. to.20.03.2019 for hearing on ad-interim relief.
    Nature Of Disposal: OTHERWISE
    Disposal Date: 13-03-2019

    Additional Case Details

    Additional Case Details
    Filing Number: 102825/2019
    Filing Date: 06-03-2019
    First Hearing Date: 13th March 2019
    Decision Date: 13th March 2019
    Court Number And Judge: 4-COURT 04 ADDL SESSIONS JUDGE

    Orders

    1
    Final Order 1
    13 Mar 2019
    Order Details: Other
    Pdf Text: IN THE COURT OF :COURT 4 ADDL SESSIONS JUDGE
    Case No. :DELAY CONDONATION APPL/0100068/2019
    M/s. Decent Soap Factory Pvt. Ltd. in Misc. Appeal St. No.2824 of 19 Vs MCGM
    Date : 13-03-2019
    Business : Adv. D.A. Thorat for appellant present. Adv. for respondent
    present. Heard the Ld. adv. for appellant as well as the Ld.
    adv. for respondent. The Ld. adv. for respondent has
    submitted that sufficient opportunity has been given and the
    delay has not been explained. I have examine the
    submissions of the parties. The delay does not to be
    appeared inordinate. Only 5 days delays is there. With a
    view that the appellant may be heard on merits, the delay
    may be condoned. Hence, the delay occurred filed is appeal
    is condoned on the appellant paying cost of Rs. 1,000/- to
    the DLSA. Mumbai. In these terms, the application for
    delay stands disposed off. Appeal be registered and be
    placed before the court for hearing the parties on ad-interim
    relief. Matter is adjd. to.20.03.2019 for hearing on ad-
    interim relief.
    Nature of Disposal : OTHERWISE
    Disposal Date : 13-03-2019
    COURT 4 ADDL SESSIONS JUDGE
    -- 1 of 1 --