Full Order Text
Final Order 1 · 11 Feb 2020 · CNR MHCC010021492019
Order Details: Copy of Judgment Pdf Text: SJ 61/2019 IN SUM.SUIT 1280/2018 1 IN THE CITY CIVIL COURT AT MUMBAI SUMMONS FOR JUDGMENT 61 OF 2019 IN SUMMARY SUIT NO. 1280 of 2018 (UNDER ORDER XXXVII THE CODE OF CIVIL PROCEDURE 1908) ( CNR NO.: MHCC01-002149-2019) M/s.Oasis Infrastructure Pvt.Ltd. A Private Limited Company constituted under Indian Companies Act 2013 having his Registered office at B-120, Shrikant Chambers, Near R.K.Studio, Sion Trombay Road, Chembur, Mumbai-400071. India. ...Plaintiff Versus 1. M/s. Extreme Engineering a proprietary firm having its office at 7, Muktanand Society,Narmada Nagar, Bharuch- 392 015 And M/s. Extreme Engineering 423, 3rd floor, Orian Arcede, Zadeshwar Road, Bharuch-392 015. 2. Deep Agrawat Age: Adult, Occupation: Business Proprietor of M/s.Extreme Engineering, Bharuch- 392 015. ...Defendants Appearances:- Advocate Ms.Pooja Dhumal for the Plaintiff. Advocate Ms.Sumi Soman for the Defendants. CORAM : HIS HONOUR JUDGE DEEPAK L. BHAGWAT (C.R.NO.28) DATE : 11th February 2020 -- 1 of 9 -- SJ 61/2019 IN SUM.SUIT 1280/2018 2 J U D G M E N T 1. This is Summons for Judgment for recovery of Rs.11,34,457/- (Rupees Eleven Lakhs Thirty Four Thousand Four Hundred and Fifty Seven Only) with Pendente Lite and future interest at the rate of 21% p.a.. 2. According to the plaintiff, it is a service provider doing business of supply of cranes on hire basis. Defendant No.1 is a proprietary concern whereas defendant No.2 is the proprietor of defendant No.1. The parties entered into agreement vide work order bearing No. EXTREME ENGINEERING/OIPL/12/2017-2018 dated 16/11/2017 by which the defendants hired a crane at their work site from the plaintiff. The defendants were to pay monthly charges of Rs.1,70,000/-. The minimum hiring period was agreed to be 6 months once the crane reaches the site. The mobilization and de-mobilization charges were also agreed to be Rs.4,00,000/- each. However, it was agreed that if the crane works for more than 6 months de-mobilization charges shall be nil. Vide e-mail dated 20/11/2017 the plaintiff acknowledged receipt of cheque of Rs.3,70,000/-and raised the mobilization invoice, to which the defendants given the confirmation vide e-mail dated 01/12/2017. The crane started working on 01/12/2017. The crane was de-hired on 28/05/2018, thus, the de-hiring was before conclusion of 6 months. As such, the defendants were liable to pay de-mobilization charges of Rs.4,00,000/-. The plaintiff raised the bills as per the details mentioned in para 6 of the plaint. The outstanding, due and payable amount by the defendants was Rs.10,58,344/-. The plaintiff vide reminder dated 26/06/2018 demanded the said amount. The defendants vide e-mails dated 26/05/2018, 04/07/2018, 05/07/2018 replied that the -- 2 of 9 -- SJ 61/2019 IN SUM.SUIT 1280/2018 3 outstanding dues are only of Rs.2,55,040.70. The plaintiff also issued legal notice dated 14/08/2018, however, the defendants did not make the payment. At the institution of the suit the due and payable amount by the defendants was Rs.11,34,457/-, i.e Rs.10,58,344/- as principal amount and Rs.76,113/- as amount towards interest at the rate of 21% p.a.. Therefore, the plaintiff claimed recovery of said amount with the interest thereon. 3. The defendants filed reply contesting the summons for judgment. The defendants submitted that the suit is not within jurisdiction of this court. It is contented that vide work order dated 15/11/2017 they were awarded the contract by L & T to install pipes for 7.20 kms. at the rate of Rs.3590/- per meter at Madhya Pradesh. To execute the said work the crawler crane was required. The defendants had indicated to the plaintiff their requirement for Hitachi K.H. 150-40 M.T. crawler crane as well as about the time frame for the completion of the said project. The crane was to work for 26 days in a month for 10 hours per day. It was agreed that the crane will erect 6 pipes each day. There was mutual understanding between the parties that the crane should reach the site on 20/11/2017 and commence the work at the earliest. However, the plaintiff failed to comply with it. The crawler crane reached the site on 27th November, it was assembled on 30th November and while unloading the first pipe on same day the crane broke down and continued to remain so till 01/12/2017. Thus, right from the inception the plaintiff failed to adhere to the terms. Thereafter, also the crane broke down on 5th December and again on 8th December. Thus, there were repeated break down of the crane. Consequently, the project was affected and defendants had to seek extension from L & T company for completion of the project on 16/12/2017. The defendants had intimated, by e-mail, to -- 3 of 9 -- SJ 61/2019 IN SUM.SUIT 1280/2018 4 the plaintiff the effect of defective crane on the project. The crane remained in break down state till 28/12/2017. Therefore, the image of defendants was tarnished before the L & T and it also caused huge financial loss to the defendants. On 29/12/2017, the plaintiff provided tyre mounted crane as the defects in the crawler crane were not rectified. However, the working phase of tyre mounted crane was low then that of crawler crane which further affected the project. The defendants, contended that due to defective and faulty crane provided by the plaintiff the project was delayed and ultimately L & T cut shot the contract from installation of pipes from 7.20 kms.to 3.5 kms. which resulted into loss of Rs.12,66,552/- due to difference in the performance capacity between tyre mountain crane and crawler crane. The defendants also suffered loss of Rs. 38,59,968/- due to cut short of the project by L & T. The crane was directed to be de-mobilized only after a period of 6 months from the date of commencing of the work. Therefore, the plaintiff cannot claim de-mobilization charges. Thus, the defendants on these grounds requested to grant unconditional leave to defend. 4. Considering material on record and submissions made on behalf of the parties points arise for determination alongwith my findings thereon are as under:- POINTS FINDINGS 1. Whether the plaintiff is entitled to Summons for Judgment? In the Negative 2. Whether the defendant is entitled to Leave to defend? If yes, whether conditional/ unconditional? Unconditional Leave to defend 3. What order? As per final order. -- 4 of 9 -- SJ 61/2019 IN SUM.SUIT 1280/2018 5 R E A S O N S AS TO POINTS NO.1 TO 3 5. The Ld. Advocate on behalf of the plaintiff argued that the defendants admitted the agreement dated 16/11/2017 between the parties. The execution of the work is also admitted. Thus, the liability has been admitted. Therefore, he requested to allow the summons for judgment. 6. On the other hand, the Ld.advocate on behalf of the defendants argued that the crane had been hired for the work at Madhya Pradesh. The defendants office is situated at Bharuch beyond the jurisdiction of this court. Thus, this court has no jurisdiction to try and entertain the suit. She argued that due to break down of the crane and supply of the tyre mounted crane the work could not be effectively completed as required. Resultantly, the defendants suffered financial loss. The crane was at the site for 6 months. Therefore, the defendants are not liable to pay the de-mobilization charges. All these contentions raised triable issues. The defendants have substantial defence. Therefore, she requested to grant unconditional leave to defend. 7. It is not disputed that the defendants hired crane machine from the plaintiff vide agreement dated 16/11/2017. Admittedly, the work has been executed at Madhya Pradesh. The defendants office is also situated in Bharuch. However, the work order dated 16/11/2017 shows that it was addressed and issued to the plaintiff at the address of Mumbai. Once the work order was issued from the defendants office it was accepted by the plaintiff from his office. The part of the -- 5 of 9 -- SJ 61/2019 IN SUM.SUIT 1280/2018 6 negotiations and the formations of the contract took place at Mumbai. Therefore this court has jurisdiction. 8. However, so far as defence that the defendants suffered financial loss and the plaintiff did not adhere to the terms and conditions of the contract, this court must note that the basic work order speaks that the defendants had put the requirements of the Hitachi K.T.150 40 MT Crawler Crane. Thus, the specification as put by the defendants in the work order apparently shows that the defendants had insisted on Hitachi Crawler Crane. Further the work order does not specify as to the date from when work was to be started. The defendants contention is that the crane was to reach the site on 20/11/2017. However, it reached the site on 27/11/2017. Thus, the machine did not reach the site as required by the defendants. Now whether there was such mutual agreement between the parties is the matter of evidence. Further contention of the defendants is that the crane, since inspection, went into break down state. The operation-cum Hirer's Representative report at page 28 with the plaint shows that the crane was in break down state from 08/12/2017 till 22/01/2018. Thus, at this stage, there is substance in the contention of the defendants that since inspection the crawler crane went into break down state. The further reports also show that the machine was in break down on 17/02/2018, 18/03/2018, 19/03/2018, 20/03/2018. The defendants in their reply elaborately mentioned the actual work of the cranes during each of the months from the December 2018 to May 2018. Now whether the crane remained in the break down state as contented by the defendants is the matter of evidence. However, at this stage, there is substance in the contention of the defendants that the crane remained in break down state for some period. Further whether due to the replacement of the -- 6 of 9 -- SJ 61/2019 IN SUM.SUIT 1280/2018 7 crawler crane by hire mountain crane the defendants could not effectively complete the project, whether L & T cut short the project and whether the defendants suffered the loss are all these triable issues. The copy of e-mail dated 16/12/2017 issued by the defendants to the plaintiff also shows that the defendants had put grievance about the non working of the crane. It was also stated in the same e-mail that the execution of the project has been delayed and the defendants reputation is spoiled. Thus, since the very initial phase of the performance of the contract, the defendants had put their grievance regarding quality of the crane. The reply mail issued on behalf of the plaintiff on same date shows that the duration of the crane break down exceeded due to non availability of the part in Madhya Pradesh. In other words, apparently, the plaintiff admitted that the crane went into break down and it could not be restarted immediately or within reasonable period. Having regard to this contentions and the nature of the material on record the defendants put the defence with substance and with the triable issues. Resultantly, unconditional leave deserves to be granted to the defendants and the plaintiff is not entitled to the summons for judgment. Hence, point No.1 is answered in the negative and point No.2 is answered as defendants are entitled to unconditional leave to defend. In view of point No.3 order as follows is passed:- ORDER 1. The summons for judgment No.61/2019 is rejected. 2. Unconditional leave to defend is granted to the defendants. 3. The defendants shall file written statement on or before 06/04/2020. 4. The Registrar shall cause the conversion of the suit to appropriate -- 7 of 9 -- SJ 61/2019 IN SUM.SUIT 1280/2018 8 category and to assign it to appropriate court by completing the requisite process. 5. The Summons for judgment No.61/2019 is disposed. (Deepak L. Bhagwat) Ad-Hoc Judge, Date: 11/02/2020 City Civil Court, Gr. Mumbai Dictated on : 11/02/2020 Signed on : 15/02/2020 CERTIFIED TO BE TRUE AND CORRECT COPY OF THE ORIGINAL SIGNED JUDGMENT/ORDER.” 20/02/2020 at 11.20a.m. Mrs.J.V.Pawar UPLOAD DATE AND TIME NAME OF STENOGRAPHER Name of the Judge (With Court Room No.) HHJ Shri.D.L.Bhagwat (C.R.NO.28) Date of pronouncement of Judgment/Order 11/02/2020 Judgment/Order signed by P.O. on 15/02/2020 Judgment/Order uploaded on 20/02/2020 -- 8 of 9 -- SJ 61/2019 IN SUM.SUIT 1280/2018 9 -- 9 of 9 --
