Full Order Text
Order 1 · 12 Jun 2019 · CNR MHCC010003492019
Order Details: Notice of Motion Pdf Text: 1 IN THE COURT OF CITY CIVIL COURT AT GR.BOMBAY NOTICE OF MOTION NO.128 OF 2019 IN S.C. SUIT NO.06 OF 2019 1. Praful Kanubhai Merchant 2. Pratapa Jivandas Kapadia ..Plaintiffs Versus 1. Shrikant Govind Kamat 2. Kanubhai Purshottam Merchant ..Defendants Ld. advocate Mr.Barot for the plaintiffs Ld. advocate Mr.Prerak Sharma for defendant no.1 CORAM: HIS HONOUR JUDGE SHRI M.SALMAN AZMI DATE: 12/06/2019 ORAL ORDER 1. The plaintiffs have taken out this Notice of Motion interalia claiming temporary injunction for restraining defendant no.1, his servant, agent from obstructing and/or preventing the contractor and workers of NOC holders i.e. plaintiffs to carry out repairs to the back portion of shop no.1 and above portion of suit property namely Keshav Bhavan, 241, JSS Road, Mumbai400 004 till disposal of the suit. 2. At the outset it is necessary to address factual matrix of the case. 3. It is the stand of the plaintiffs that there is Keshav -- 1 of 9 -- 2 building having ground plus four floors situated at 241, JSS Road, Mumbai. In all there are eight tenants. Defendant No.1 is also one of the tenant of the commercial premises. The M.B.R & R board has granted NOC dated 29/10/2013 to carry out repairs of the suit building. Accordingly, the Municipal Corporation of Gr. Mumbai(in short 'MCGM') has issued IOD dated 04/06/2015 and sanctioned the repair plan in favour of NOC holders. The NOC holders are plaintiffs and defendant no.1. The plaintiffs and defendant no.1 have given undertaking to carry out the repairs as per rules. The architect was appointed and accordingly repair plan was submitted to MCGM and IOD has been granted in favour of NOC holders. All the tenants have contributed their share for repairs but defendant no.1 was defaulter in contributing his share towards the repairs. The repair work of the suit property was carried out by NOC holders. However, the back portion of shop no.1 occupied by defendant no.1, the repairs from back portion ground floor to upper floors are required to be carried out. The back portion of shop no.1 and above portion of suit property have been demolished for the purpose of carrying out repairs. The defendant no.1 with malafide intention did not allow the contractor and workers to carry out the repairs by not permitting the contractor to put column and beam from the back -- 2 of 9 -- 3 portion of shop no.1 whereby defendant no.1 has obstructed the repairing work of the suit property. The notice was accordingly issued. In this background the suit came to be filed. 4. Defendant no.1 resisted the claim of the plaintiffs by filing written statement. Defendant no.1 claims that he has handed over the possession of the premises to defendant no.2 and plaintiff no.1 on 08/03/2013 so as to enable them to repair the gallery section which was in poor condition. Under the guise of repairing the gallery section, defendant no.2 and plaintiff no.1 had also requested defendant no.1 to allow them to remove the rolling shutter gate of the restaurant premises so as to enable them to carry out the repair work. They assured that repair work would be completed within a week. After removal of the rolling shutter the contractor engaged by defendant no.2 and plaintiff no.1 dumped 200 bags of cement, 2000 bricks, and bags and other construction materials such as iron rods, beams, channels and other construction equipment in the restaurant premises thereby virtually converting the same to a godown for storing construction material. The whole building was covered with scaffolding comprising of bamboo sticks. Therefore the restaurant premises became virtually useless for the purpose of carrying on the business. Plaintiff no.1 and defendant no.2 are the landlords and assured that entire renovation -- 3 of 9 -- 4 work would be completed in a short span and defendant no.1 would be put back in possession of the restaurant premises as it then was. The defendant no.1 has cooperated them for jointly applying for NOC from MHADA for the purpose of carrying out the repair work. He is also one of the NOC holder. After obtaining the NOC from MBR & R the plaintiff and defendant no.2 cut off the contacts with defendant no.1. They have engaged the contractor of their choice. They did not provide information as regard the repair work. Despite the lapse of more than five and half years, the plaintiffs and defendant no.2 have failed to complete the repairs work and therefore they are responsible for the delay. 5. There are gross discrepancies in the repair work as depicted in the repair plan and actual repair work being carried out on site in the suit property. He has denied the contention raised by the plaintiffs and submitted that he has contributed Rs.1.80 lacs towards the repair work and denied wrongfully obstructing the repair work. 6. On the rival submissions of the parties, following points arise for my determination and findings to it are recorded for the reasons stated to follow: POINTS (i) Whether the plaintiffs have made out a prima facie case? -- 4 of 9 -- 5 (ii) Whether the balance of convenience lies in favour of plaintiffs? (iii) To whom the irreparable loss would be caused? (iv) What order? FINDINGS (i) In the negative. (ii) In the negative. (iii) Not to the plaintiffs. (iv) As per final order REASONS Point Nos. 1 to 3 7. It is the contention of the plaintiffs that the construction is undertaken after the grant of NOC and as per sanctioned plan. The contractor and architect have been appointed by the plaintiffs and defendant no.1 as NOC holders. The architect had obtained NOC and IOD from the Competent authority. The parties are not at dispute that the NOC was granted jointly in the name of the plaintiffs and defendant no.1. On perusal of the documents annexed by the plaintiffs it reflect that the commencement certificate was issued on 24/02/2016 and it was valid up to 23/02/2017. It appears that repair work ought to have been completed on or before 23/02/2017. There is nothing on record to suggest that the time was -- 5 of 9 -- 6 extended since then for getting the repairs work completed. It is the claim of the plaintiffs that the work undertaken by them is as per the sanctioned plan and in order to support their case they have filed the photographs. On the contrary, the contention of defendant no.1 is that photographs cannot be the basis to show that construction is as per sanctioned plan. It is the further contention of the plaintiffs that there was conversation between plaintiff no.1 and defendant no.1 and from it, it reveals that the obstruction by defendant no.1 is to avoid the payment of the repairing costs of shop no.1. The plaintiffs and defendant no.1 are the NOC holders and they have to carry out the construction as per the NOC and sanctioned plan. From the documents filed by the plaintiffs, it appears that as on date there is no valid permission and the time period for carrying out the repairs has been expired on 23/02/2017. Thus there is no prima facie case made out by the plaintiffs to carry out the legal repairs. 8. Defendant no.1 has also given undertaking. The undertaking given is not a formality. The undertaking filed is meant for carrying out the repairs as per the requirements of the plans which are required to be submitted with MBBR & R boards and as per the rules, the NOC holders are responsible if any unauthorized work is done. As on date as -- 6 of 9 -- 7 pointed above, there is no extension of time for carrying out the repairs of the suit property. So, it cannot be said that the authorized work was carried out. Defendant no.1 who is also NOC holder is also liable for the consequences of the same. Thus, in this background, it appears that balance of convenience does not lie in favour of the plaintiffs. 9. The plaintiffs have made vague statement in the plaint as regard obstruction by defendant no.1 for restraining them or contractor from carrying out the repair work. There is no date and time on which and in what manner, defendant no.1 has restrained the contractor or workers. The notice was issued to defendant no.1 by the plaintiffs on 26/09/2018 and suit was filed after the period of three months. Even the notice is silent about the date and time and manner in which the obstruction was made. Considering the said factor and the vague statement and absence of extension of time for carrying out the work, it appears that there is no irreparable loss which will be caused to the plaintiffs. Thus, in view of the above discussion, the plaintiffs have not made out any case for grant of temporary injunction. Hence, I am inclined to answer point nos.1 to 3 in the negative. POINT NO.4 10. In view of the above discussion, the Notice of Motion deserves to be rejected. Accordingly, it is -- 7 of 9 -- 8 expedient to pass following order: ORDER Notice of Motion No.128/2019 stands rejected. 12/06/2019 M.SALMAN AZMI CITY CIVIL COURT, GR.MUMBAI. Dictated on : 12/06/2019 Transcribed on : 14/06/2019 Signed on : 15/06/2019 'CERTIFIED TO BE TRUE AND CORRECT COPY OF THE ORIGINAL SIGNED JUDGMENT/ORDER”. 17/06/19 at 4.00 pm. MRS.T.C.KAMBLE Name of the Judge HHJ SHRI M.S.AZMI, CR NO.16 Date of Pronouncement of judgment/order 12/06/2019 Judgment and order signed by P.O. 15/06/2019 Judgment/order uploaded on 17/06/2019 -- 8 of 9 -- 9 -- 9 of 9 --
