NOTICE OF MOTION

M/s. L.P. India Logistics Pvt. Ltd.VsMr. Abdullah Habib Sunesara +1 more

CNR MHCC01000339201828-COURT 28 ADD SESSIONS JUDGE
City Civil Court, Mumbai
Mumbai · Maharashtra (MH)
CASE DISPOSED
Uncontested--ALLOWED
Decision Date: 04th June 2018

TrustJury record updated 22 Sept 2026

Case Overview

Registration Number
100100/2018
Registration Date
09 Jan 2018

Advocates

1

For Petitioner

    Not available

    For Respondent

    Parties

    3

    Acts & Sections

    1
    Public Premises (Eviction of Unauthorised Occupants) Act · Sec 9

    Case History / Proceedings

    Case History
    Date: 09-02-2018
    Business: Adv. Mr. Ramesh Gupta for plaintiff present.
    Adv. Mr. Madan Gupta for  defendant present.
    Adv. for plaintiff tendered original S/J No.162/17 along with affidavit in support of S/J it is t.o.r
    Ld. adv. for plaintiff filed reply to N/M No.1357/17 and 100/18.
    Both the Ld. advs. argued N/M No.1357/17 and 100/18
    Matter is adj. to 23/03/2018 for Order on N/M No.1357/17 and 100/18.
    Next Purpose: NM  ORDERS
    Next Hearing Date: 23-03-2018
    
    Date: 23-03-2018
    Business: Representative plaintiff present.
    Adv. Ms. Sujata Natekar for plaintiff present.
    None for the defendant.
    KB later on at 1.55pm.
    Adv. Mr. Gupta for plaintiff present.
    None for the defendant.
    Order -
    Nm. No. 1357/17 allowed.
    Matter is adj. to 04/06/2018 for NM hearing.
    Next Purpose: NM FOR HEARING
    Next Hearing Date: 04-06-2018
    
    Date: 04-06-2018
    Business: Adv. Vijay Vaghela for plaintiff present.
    Adv. Mukesh Pabari for defendants present.
    Read. Heard.
             It appears that there is a delay of 177 days. Considering the reasons mentioned in the application, it appears that Aplnt has shown the sufficient cause for condoning the delay. It appears that delay is no caused due to negligence and in action  on the part of Aplnt. Hence, the interest of justice requires to condone the delay. Hence, following order is passed
                 ORDER
    1. Application is allowed.
    2. The delay caused, is hereby condoned.
    3. The Notice of motion no.100/18 made absolute, subject to cost of Rs.1500/- payable by the defendant to plaintiff.
    Matter is adjd. to 19/06/2018 for  S/J hearing.
    Nature Of Disposal: ALLOWED
    Disposal Date: 04-06-2018

    Additional Case Details

    Additional Case Details
    Filing Number: 100383/2018
    Filing Date: 09-01-2018
    First Hearing Date: 09th February 2018
    Decision Date: 04th June 2018
    Court Number And Judge: 28-COURT 28 ADD SESSIONS JUDGE

    Orders

    1
    Final Order 1
    04 Jun 2018
    Order Details: Notice of Motion
    Pdf Text: IN THE COURT OF :COURT 28 ADD SESSIONS JUDGE
    Case No. :NOTICE OF MOTION/0100100/2018
    M/s. L.P. India Logistics Pvt. Ltd. Vs 1.Mr. Abdullah Habib Sunesara 2.Mr. Riyaz Sunesara
    Date : 04-06-2018
    Business : Adv. Vijay Vaghela for plaintiff present. Adv. Mukesh
    Pabari for defendants present. Read. Heard. It appears that
    there is a delay of 177 days. Considering the reasons
    mentioned in the application, it appears that Aplnt has
    shown the sufficient cause for condoning the delay. It
    appears that delay is no caused due to negligence and in
    action on the part of Aplnt. Hence, the interest of justice
    requires to condone the delay. Hence, following order is
    passed ORDER 1. Application is allowed. 2. The delay
    caused, is hereby condoned. 3. The Notice of motion
    no.100/18 made absolute, subject to cost of Rs.1500/-
    payable by the defendant to plaintiff. Matter is adjd. to
    19/06/2018 for S/J hearing.
    Nature of Disposal : ALLOWED
    Disposal Date : 04-06-2018
    COURT 28 ADD SESSIONS JUDGE