Order Details: COPY OF JUDGMENT
Pdf Text: IN THE COURT OF SH. RAMESH KUMAR-II,
ADDITIONAL DISTRICT JUDGE-01
SHAHDARA DISTRICT, KARKARDOOMA COURTS:
DELHI
LAC No.3/2023
IN THE MATTER OF:-
(As per amended memo of parties)
Sh. Suresh Chander Vij
S/o Late Sh. Desh Raj Vij
R/o D-242, Second Floor,
Anand Vihar, Delhi-110092.
.........Petitioner
Versus
1. Union of India
Through Secretary
Land And Building
Nirman Bhawan,
Through D.C.
Govt. of N.C.T. of Delhi
2. D.M.R.C.
(Delhi Metro Rail Corporation)
New Delhi.
.........Respondents
Date of Institution : 01.09.2008
Date of reserving judgment : 25.03.2023
Date of judgment : 28.03.2023
LAC No.3/2023 Page no. 1/9
-- 1 of 9 --
JUDGMENT
1 Vide this judgment, this Court shall decide the reference
petition filed under section 18 of Land Acquisition Act, 1894
(hereinafter referred to as 'L.A. Act, 1894') arising out of award
dated 20.07.1999 with respect to village Chandrawali @ Shahdara,
Delhi.
2 For deciding the reference U/s 18 of the Land Acquisition
Act, 1894 (In short LA Act) r/w statement U/s 19 of the Act sent
by the LAC Delhi, the relevant dates and facts which are
necessary for adjudication in the present matter are being given
herein-under:-
i) Date of notification U/s 4 of the Act :12.06.1997
ii) Date of notification U/s 6 & 17of the Act :28.07.1997
iii) Date of award :20.07.1999
iv) Area of the locality :Chandrawali @ Shahdara
v) Project :For the purpose of Delhi
Metro Rail Corporation
vi) The land use of the area as per the award :Residential
vii) Petition referred to court on :01.09.2008
3 The facts leading to the filing of the present petition are
that the petitioner was an interested person being owner and in
possession of 407 sq. mtrs. of land situated at Village
Chandrawali, known as Railway Road Shahdara which was
acquired vide award No.1/1999-2000. The petitioner further
contended that the property was being used for commercial
purposes for the last more than 45 years and the petitioner has
been granted various licenses to run a factory on the acquired
property and there were number of shops existing on the acquired
property as on the date of notification U/s 4 of the LA Act. The
LAC No.3/2023 Page no. 2/9
-- 2 of 9 --
petitioner further contended that he along with his brothers was
running a factory and the Govt. had duly granted a license in the
year 1952 and therefore the acquired property was not residential
by any stretch of imagination. The petitioner further contended
that the market value assessed by the LAC was very low and was
not the actual market value prevailing in the area as on the date of
notification U/s 4 of LA Act. The petitioner was one of the legal
heirs of the original owner Sh. Deshraj Vij who died on
24.08.1998 and the petitioner was accordingly entitled to 1/3rd
share in the acquired property.
4 It has further been further averred by the petitioner that the
market value of his property was not less than Rs.56,000/- per sq.
yds. as on the date of notification U/s 4 of the LA Act. The land
of the petitioner has been wrongly treated as residential instead of
being treated as commercial and thus the LAC has undervalued
the market value. The petitioner has further contended that the
acquired property was situated at Shahdara in the main market
known as Railway Road and the entire area is being used as a
commercial market since the year 1952. The LAC has also
admitted in the award that the shops were situated in the area but
even then the LAC has wrongly assessed the market value on
residential basis. The petitioner has further contended that the
LAC has wrongly held that MCD had not declared the area as
commercial whereas in the year 1969, the entire area has already
been declared as commercial by the DDA. The petitioner has
further contended that the cost of construction has also been fixed
wrongly by the LAC.
5 The notification dated 12.06.1997 under Section 4 of the
LAC No.3/2023 Page no. 3/9
-- 3 of 9 --
L.A. Act, 1894 was issued by the Land Acquisition Collector
(hereinafter referred to as "LAC") for acquisition of the acquired
property for the purpose of Mass Rapid Transport System
[MRTS], Delhi at Chandrawali @ Shahdara which was followed
by the Notification dated 28.07.1997 under Section 6 & 17 (1) of
L.A. Act, 1894. Keeping in view the use of the land under
acquisition, residential L&DO rates which were issued by the
Ministry of Urban Development pertaining to different areas of
Delhi w.e.f. 1.4.1996 for Zone 5 was assessed by the LAC and
accordingly the LAC assessed an amount of Rs.2,805/- per sq.
mtrs. Further, solatium at the rate of 30% of market value
alongwith the additional amount @ 12% of market value w.e.f.
12.06.1997 to 20.07.1999 was allowed apart from cost of structure
appended to the said land and statutory interest under Section 34
of Act. Thus, an Award for total amount of Rs.18,48,55,526/- was
passed by the LAC.
6 Being aggrieved from the lesser rate fixed by the LAC for
the acquired land, the petitioner filed a petition under Section 18
of L.A. Act, 1894 before the LAC. The LAC sent the present
reference petition to this court for adjudication and court
notices were issued to the parties and thereafter, on
01.10.2008, DMRC was impleaded as necessary and proper party
in this reference being the beneficiary of the acquired land.
Subsequently the present case was listed for trial and finally after
adjudication of the evidence filed by all the parties, Ld.
predecessor of this court finally announced an award/ judgment
dated 07.09.2016 in which he relied upon the circle rates notified
under the provisions of Delhi Stamp [Prevention of
LAC No.3/2023 Page no. 4/9
-- 4 of 9 --
Undervaluation of Instruments] Rules 2007 and enhanced the
market value from Rs.2805/- to Rs.5865/- per sq. mtrs..
7 Separate written statement was filed on behalf of
respondent nos. 1 and 2. Both the respondents took various pleas
in their written statement and averred that the market value
assessed by the LAC was completely fair and had been
assessed after considering the existing market value,
locality, situation of area, quality, potentiality and the use of
the land in question. The respondents also stated that the
acquired property was being used for agricultural purposes
and the petitioner was not entitled for any enhancement.
8 The present case has been passed through two rounds of
litigation. My Ld. Predecessor had already determined/assessed
the market value of the acquired property @ Rs.5865/- per sq.
mtrs. vide judgment and decree dated 07.09.2016. The said
judgment was passed on the basis of market value assessed on the
basis of the judgment passed in case titled Chandra Pratap Singh
Vs. UOI & Anr. which was in respect of award No.2/07-08,
Jhilmil Tahirpur Delhi wherein the date of notification was
12.04.2006.
9 The said judgment was eventually challenged by the
respondent no.2 and the matter was remanded back by the
Hon’ble High Court of Delhi for adducing of additional evidence
by both the parties.
10 Vide order dated 06.12.2010, following issues were
framed by the Ld. Predecessor of this court as:-
1 Whether the petitioner is entitled for
LAC No.3/2023 Page no. 5/9
-- 5 of 9 --
compensation at the enhanced rate as claimed? OPP
2 Relief.
11 In earlier proceedings, the petitioner examined as many as
three witnesses including himself as PW1.
12 On the other hand, ld. counsel for the Union of
India/respondent no.1 tendered the copy of the award no.1/1999-
2000 pertaining to Village Chandrawali as Ex.R1 in evidence.
13 The said award Ex.R1 had been adopted by Sh. Manish
Kumar, Legal Assistant of respondent no.2/DMRC.
14 In additional evidence, the petitioner examined as many as
six witnesses including himself as PW1. The petitioner has
adopted evidence led in case titled as Subhash Chander Vij Vs
Union of India & Anr. bearing LAC No.23/16/08 and closed his
evidence on 28.02.2020.
15 The respondent no.1 did not lead any additional evidence
after the present reference was remanded to this court for
adducing additional evidence and relied upon the earlier evidence
which was the award Ex.R-1.
16 The respondent no.2, in the earlier proceedings, adopted the
evidence led by the Union of India i.e. respondent no.1, however
when the present matter was remanded back, the respondent no.2
has examined Sh. Vijay Kumar, Section Officer, Legal, DMRC,
Metro Bhawan, Barakhamba Road, New Delhi as R2W1, who
tendered in evidence certified copies of sale deeds which are
Ex.R2W1/1 to Ex.R2W1/12. Thereafter, respondent no.2 also
closed his evidence on 28.02.2020.
17 After conclusion of additional evidence of both the parties
matter was fixed for final arguments.
LAC No.3/2023 Page no. 6/9
-- 6 of 9 --
18 Ld. counsels for all the parties have filed their written
arguments in support of their respective stands and they submitted
that they do not want to submit anything else beyond written
arguments.
19 I have perused the written arguments as filed by the parties
and also perused the record. On perusal of record, my issue-wise
finding is as follows:-
ISSUE NO.1
20 Onus to prove this issue was upon the petitioner. However,
during the course of trial, the parties have apprised this court that
the market value with respect to the property acquired vide the
same notification and same award has already been decided by the
Hon’ble High Court of Delhi vide judgment dated 07.06.2019
passed in case titled UOI Vs. M.L. Gupta & Ors. in which the
Hon’ble High Court of Delhi was pleased to fix the market value
of the properties acquired vide the same notification and same
award @ Rs.4692/- per sq. mtr. along with statutory benefits. The
Hon’ble High Court of Delhi was pleased to assess the said
market value after allowing a reduction of 20% on the rate of
Rs.5865/- per sq. mtrs. which was previously determined by my
Ld. Predecessor.
21 The petitioner has contended in his written arguments that
the rate of Rs.5865/- per sq. mtrs. was assessed by my ld.
Predecessor on the basis of judgment passed in case titled Chandra
Pratap Singh Vs. UOI in which the market value was assessed as
Rs.21920/- per sq. mtrs. however the said market value has now
been enhanced to Rs.48,000/- per sq. mtrs. and based on the said
LAC No.3/2023 Page no. 7/9
-- 7 of 9 --
analogy, the market value of the petitioner ought not to be less
than Rs.25,000/- per sq. mtrs.
22 Be that as it may, this court is not inclined to go into any
evidence or judgment subsequent to the passing of the judgment
by the Hon’ble High Court of Delhi in case titled UOI Vs. M.L.
Gupta (Supra) wherein the market value for the properties
acquired vide the same notification and same award have already
been assessed @ Rs.4692/- per sq. mtrs. as on the date of
notification i.e. 12.06.1997.
23 The respondent no.2 has further argued that an SLP is still
pending before the Hon’ble Supreme Court of India with respect
to the determination of market value, however from the perusal of
the record, it is apparent that the SLP filed by the respondents has
been dismissed however the SLP filed by the petitioner therein
namely Sh. M.L. Gupta is still pending adjudication. Thus the
market value assessed by the Hon’ble High Court of Delhi has
reached finality qua the respondents.
RELIEF
24 In view of the above noted findings, the petitioner is
entitled to the market value @ Rs.4,692/- per sq. mtrs. as on
12.06.1997 with respect to their land acquired as per the statement
U/s 19 of the LA Act. In addition, the petitioner would also be
entitled to all statutory benefits i.e. 30% solatium on the market
value in view of the compulsory nature of acquisition U/s 23 (2)
of the LA Act. The petitioner would be entitled to additional
amount @ 12% per annum U/s 23 (1A) of the LA Act from the
date of notification U/s 4 of the LA Act i.e. 12.06.1997 till the date
of dispossession i.e. 20.07.1999. Besides this, the petitioner would
LAC No.3/2023 Page no. 8/9
-- 8 of 9 --
also be entitled to interest on the enhanced amount of
compensation @ 9% per annum on excess amount awarded by the
court for one year from the date of notification and thereafter @
15% per annum till the date of payment of the balance amount.
The respondents no.1 & 2 shall be jointly and severally liable to
make the payment of the enhanced amount of compensation as
determined herein-above to the petitioner.
25 The perusal of the record shows that the respondent no.2
has already deposited the enhanced amount of compensation @
Rs.5865/- per sq. mtrs. and therefore I hereby direct that any
balance amount, after payable of the decreetal amount to the
petitioner, be sent back to the respondent no.2. If however,
additional amount requires to be deposited by the respondent no.2
in terms of the present judgment, the same be remitted by the
respondent no.2 with immediate effect.
26 The reference petition stands answered accordingly. Both
the sides will bear their own costs. Decree sheet be prepared
accordingly.
27 A copy of this judgement be sent to the concerned LAC
for information and necessary compliance within three months of
its receipt. File be consigned to Record Room as per rules.
(Typed to the dictation directly corrected and
pronounced in open court on 28.03.2023).
(RAMESH KUMAR-II)
ADDL. DISTRICT JUDGE-01
SHADARA DISTRICT
KARKARDOOMA COURTS
DELHI
LAC No.3/2023 Page no. 9/9