Full Order Text
Interim Order 14 · 25 Nov 2024 · CNR DLSH010009052024
Order Details: COPY OF ORDER Pdf Text: 10CS (COMM)100/24 M/s Rysa Infratech Pvt. Ltd. Vs. The Chief Engineer Pune Zone And Anr 25.11.2024 Order on application filed by the defendant no.2 u/O 7 Rule 11 r/w Section 151 of CPC filed by the defendant no.2 1. This order of mine will dispose of an application filed by the defendant no.2 u/O 7 Rule 11 r/w Section 151 of CPC. 2. I have heard the counsels for the parties. 3. Sh. Arjun D. Singh, Ld. Counsel for defendant no.2 has submitted that the suit of the plaintiff is premature, because, as per the terms of the work order dated 11.04.2020, the payment was required to be made by defendant no.2 to the plaintiff on back to back basis and submitted that the value of the contract was Rs. 4,01,55,000/- out of which, the defendant no.2 has paid Rs. 3,78,74,550/- to the plaintiff and an amount of Rs. 22,80,450/- is yet to be paid by defendant no.1 to defendant no.2 and on receiving of the said amount, defendant no.2 will pay the said amount to the plaintiff and submitted that since this case is premature and without cause of action, as prior to the receiving of amount of Rs. 22,80,450/-, from the defendant no.1, the plaintiff has filed the present suit. He has also submitted that the plaintiff has failed to do the civil work, so, the defendant no.2 had to get the civil work done in this project from another person, so, the plaint of the plaintiff is liable to be rejected, as per provisions of Order 7 Rule 11 of CPC and prayed for allowing this application. 4. On the other hand, Sh. Chaman Sharma, Ld. Counsel for the plaintiff has submitted that the defendant no.1 and defendant no.2 had entered into a contract CS (COMM)100/24 M/s Rysa Infratech Pvt. Ltd. Vs. The Chief Engineer Pune Zone And Anr Page no. 1 of 10 -- 1 of 10 -- and the contract of total amount of Rs. 4,01,55,000/- was entered into between the defendant no.2 and the plaintiff. He has also submitted that defendant no.2 has paid an amount of Rs. 2,96,09,751/- and an amount of Rs. 73,81,953/- alongwith interest @ 18% per annum is yet to be paid by the defendants. He has also submitted that in view of some hardships, civil work in the project could not be done by the plaintiff and the plaintiff has placed on record the deductions at page no. 64 wherein, the deduction of Rs. 33,13,296.73 paise/- is mentioned (in view of not doing of civil work) and submitted that the plaintiff is not claiming the said amount of Rs. 33,13,296.73 paise/- as the plaintiff could not do the civil work in the project. He has also submitted that the counsel for defendant no.2 has submitted that an amount of Rs. 22,80,450/- is withheld by defendant no.1, but, suit amount is Rs. 73,81,953/- and submitted that if the contention of Ld. Counsel for defendant no.2 is taken to be true even then, only an amount of Rs. 22,80,450/- is alleged to have been withheld by defendant no.1. Even otherwise, defendant no.2 has failed to make payment of suit amount to the plaintiff and submitted that at the time of disposal of application u/s 7 Rule 11 of CPC, only the averments made in the plaint are required to be looked into and the defence of the defendant cannot be looked into and submitted that since from the perusal of the plaint, it is clear that the present suit has been filed by the plaintiff for recovery of Rs. 73,81,953/- alongwith interest @ 18% per annum and the cost of the suit, so, the application filed by the defendant no.2 u/O 7 Rule 11 of CPC may be dismissed. 5. I have given thoughtful consideration to the submissions made by Ld. Counsels for the parties and perused the record. 6. The perusal of the record reveals that the plaintiff has filed the present suit for recovery of Rs. 73,81,953/- stating therein that the defendant No.1 is the Chief CS (COMM)100/24 M/s Rysa Infratech Pvt. Ltd. Vs. The Chief Engineer Pune Zone And Anr Page no. 2 of 10 -- 2 of 10 -- Engineer of Pune Zone Military Engineering Services, and the defendant No.2 is a registered contractor with the Military Engineering Services, while the plaintiff is also authorized to do the work with the Military Engineering Services. 7. It is further averred that the defendant No.1 awarded the work for completion of incomplete work for construction of Command Hospital and OTM Accn. Southern Command Pune to the defendant No.2, which also include the Provisions of STPs and ETPs in “Prime Cost Sum” on which, the defendant No.2 Quoted 15% as overcharged upon the payment to be paid to the plaintiff. 8. It is further averred that the defendant No.1 nominated the plaintiff through E-tendering process conducted by the GE(I)(P)(CH) Pune under delegation and were entrusted with the responsibility of executing specialized work under PC SUM, approved by defendant No.1 on 2nd April 2020 and further formally intimated by GE(I)(P)(CH) vide their letter No. 8031/2667/E8 Dated 13/04/2020 to execute the STP & ETP work pertaining to BOQ item No.2.80 of (Pc Sum) through defendant No.2. 9. It is further averred that a formal offer was made to the defendant No.2 by the plaintiff on 09/04/2020, which was duly accepted by the defendant No.2 on 11/04/2020 and after acceptance of the offer, the defendant No.2 negotiated with plaintiff to execute the civil work of STPs and ETPs, on the basis of the payment to be made on measured actual executed quantity, since the defendant No.2 had their T&P and labor available at the site for execution of work in the main Contract, Rates and provisional quantities were agreed and signed between the defendant No.2 and plaintiff. CS (COMM)100/24 M/s Rysa Infratech Pvt. Ltd. Vs. The Chief Engineer Pune Zone And Anr Page no. 3 of 10 -- 3 of 10 -- 10. It is further averred that the plaintiff has completed the work diligently, in accordance with the tender’s conditions issued to plaintiff. However, the main contractor i.e. the defendant No.2 continuously delayed the payment during the occurrence of the work and it was intimated to the defendant no.1, time to time. And after completing the work and taking the tax paid vouchers from plaintiff, the defendant No.2 is imposing unilateral conditions and holding a huge amount causing plaintiff in severe financial strain, affected the operations of plaintiff and hampered the ability to continue working of plaintiff on the other project of Military Engineering Services. 11. It is further averred that the defendant No.2 released only Rs. 2,96,09,751/- (Rupees Two Crore Ninety Six Lakh Nine Thousands Seven Hundred and Fifty One only) against 07 RARs (Running Account Receipt) stating as received from Military Engineering Service(MES) i.e. the defendant No.1, but refused to release Balance payment of Rs. 73,81,953.00 (Rupees Seventy Three Lakh Eighty One Thousand Nine Hundred Fifty Three Only) after deducting Rs.31,63,296/- (Rupees Thirty One Lakh Sixty Three Thousand Two Hundred Ninety Six Only) on account of civil work carried out by the defendant No.2 and 1% TDS to be deducted on total contract value by the defendant no.1 and disputed the balance payment. 12. It is further averred that the tender considered for nomination under PC SUM was invited by the subordinate office of defendant No.1 with due procedure and even in the tender, the name of the main contractor was not mentioned hence all bidders submitted their bids to the subordinate office. Defendant No.1 nominated plaintiff to work with the defendant No.2 and plaintiff had worked with the defendant No.2 only because the defendant No.1 nominated to the plaintiff to CS (COMM)100/24 M/s Rysa Infratech Pvt. Ltd. Vs. The Chief Engineer Pune Zone And Anr Page no. 4 of 10 -- 4 of 10 -- work with the defendant No.2. So, the defendant No.1 is equally responsible to make the balance payment of plaintiff as per the tender. 13. It is further averred that despite of several requests by plaintiff to make the payment of balance amount of work, the defendant No.2 did not make the payment and it is very surprising for the plaintiff that the defendant No.2, instead of making the payment flatly refused to make payment vide letter No. SAM/PUN/MES/1254 Dated 22 March 2023. 14. It is further averred that the plaintiff approached the defendant No.1 to intervene and to give directions to the defendant No.2 to release the balance payment as received from the defendant No.1, but all in vain, as the defendant No.1 flatly refused to take any action against the defendant no.2 vide letter No.84408/PNA/Vol-32/2916/E8 dated 11/04/2023, and said that delay in releasing of payments and alleged final payment not released by the defendant No.2 is governed by commercial transactions entered between the defendant No.2 and plaintiff and therefore this office cannot dictate or release or withhold any payment likely to be released to the defendant No.2 by the defendant No.1. 15. It is further averred that the plaintiff in response again requested to the defendant No.1 vide letter No. RIPL/DL/SAM/CH-STP/2023/49 Dated 12/04/2023 to review the matter with copy to Chief Engineer Southern Command with request to intervene in the matter to resolve the issue to protect the right of plaintiff. But till date the situation remains unsolved and plaintiff has not had any communication with any of the defendants. CS (COMM)100/24 M/s Rysa Infratech Pvt. Ltd. Vs. The Chief Engineer Pune Zone And Anr Page no. 5 of 10 -- 5 of 10 -- 16. It is further averred that seeing no alternate, the plaintiff had sent a legal notice to the defendants through his counsel dated 16/10/2023 demanding the above mentioned dues, but the defendants did not comply the same, despite of due service of the above said notice. Thereafter the plaintiff filed a pre-institution mediation before the pre-mediation authority on dated 12/12/2023, but the defendant refused to participate in the mediation process and authority issued the report of Non-Starter on dated 11/01/2024. 17. The plaintiff has also given the details of cause of action arose to it to file the present case against both the defendants, which is to be discussed hereinafter and prayed for passing a decree for recovery of Rs. 73,81,953/- alongwith interest @ 18% per annum till the realization of the said amount alongwith cost of the suit, in favour of the plaintiff and against the defendants. 18. On the issuance of the summons to the defendants, the defendant no.2 has put it’s appearance, filed the written statement and contested the case of the plaintiff on the various grounds and filed the application under consideration and sought rejection of the plaint on the ground that the suit of the plaintiff being premature and without any cause of action. The Ld. Counsel for the defendant no.2 has submitted that as per the work order dated 11.04.2020 the payment by the defendant no.2 to the plaintiff was required to be made back to back basis and submitted that term 8 is also mentioned in the said work order to this effect and submitted that since an amount of Rs.3,78,94,500/- has been received by the plaintiff from defendant no.2 and in view of withholding of balance amount of Rs.22,80,450/- by the defendant no.1, the defendant no.2 could not make payment to the plaintiff and submitted that prior to the receiving of the amount by the defendant no.2 from defendant no.1, the plaintiff could not file the suit against the defendant no.2 and submitted that the suit of the plaintiff CS (COMM)100/24 M/s Rysa Infratech Pvt. Ltd. Vs. The Chief Engineer Pune Zone And Anr Page no. 6 of 10 -- 6 of 10 -- may be dismissed, as per provisions of Order 7 Rule 11 CPC, being premature and without cause of action. 19. Ld. Counsel for the plaintiff has controverted said submissions and submitted that at the time of disposal of application u/o 7 rule 11 CPC, only averments made in the plaint are required to be looked into and submitted that from the averments made in the plaint, it is crystal clear that the plaintiff has valid cause of action to file the present suit against the defendant no.2 also. 20. The perusal of the plaint reveal that the plaintiff has filed the present suit for recovery of Rs.73,81,953/- against both the defendants and para no.12 of the plaint reveals that the plaintiff has averred therein that the cause of action arose to the plaintiff to file the present case against the defendants on 13.04.2020, when the defendant no.1 nominated to the plaintiff through e-tendering process conducted by GE(1)(P)(CH) Pune under the delegation and entrusted with the responsibility of executing specialized work under the PC SUM approved by defendant no.1 on 02.04.2020 and further formally implemented by GE(1)(P)(CH) Pune vide their letter no.8031/2667/8E dated 13.04.2020 to execute STP and ETP work pertaining to BOQ item no.2.80 (PC SUM) through defendant no.2. It is also averred that cause of action further arose, when the plaintiff had completed the work diligently, in accordance with the condition of the tender issued to the plaintiff. It is further averred that the main contactor i.e. defendant no.2 continuously delayed the releasing of the payment during the concurrence of the work and it was intimated to the defendant no.1, from time to time and cause of action further arose, when, despite of several request made by the plaintiff to make payment of balance amount of the work,the defendant no.2 did not make the payment and defendant no.2 flatly refused to make payment to the plaintiff, vide letter no. SAM/PUN/MES/1254 dated 22.03.2020, it is also averred that CS (COMM)100/24 M/s Rysa Infratech Pvt. Ltd. Vs. The Chief Engineer Pune Zone And Anr Page no. 7 of 10 -- 7 of 10 -- cause of action further arose, when the plaintiff approached to defendant no.1 to intervene and give direction to defendant no.2 to release the balance amount, as received from defendant no.1, but, the defendant no.1 flatly refused to take any action against the defendant no.2, vide letter no.84404/PNA/VOL-32/2916/E8 dated 11.04.2023 and cause of action also arose in favour of plaintiff and against defendants, when, the plaintiff sent legal notices to the defendants through his counsel dated 16.10.23 and demanded the due amount, but, the defendants did not comply with the same despite of service of notices and cause of action also arose against the defendants to file the present suit 11.01.2024, when the defendants refused to participate in the mediation proceedings. 21. Since in the case in hand, the defendant no.2 has taken the plea that in view of withholding of an amount of Rs.22,8450/-, the suit of the plaintiff is without any cause of action, but, as the plaintiff has averred in the plaint, different dates, when the cause of action arose to it to file the present case against the defendants and the plaintiff has filed the present suit for recovery of Rs.73,81,953/- and the defendant no.2 claims that it’s amount of Rs.22,80,450/- is withheld by the defendant no.1. Thus, the amount claimed to be withheld by the defendant no.1 of defendant no.2 is not similar to the suit amount. 22. Since their Lordship of High Court in case of Tilak Raj Bhagat Vs. Ranjit Kaur & Ors. 2012 VAD (DELHI) was pleased to hold that:- “wherein it has been held that it may be worthwhile to mention here that while considering an application under order 7 rule 11 of CPC , the court has to look at the averments made in the plaint by taking the same as correct on its face value as also the documents filed in support thereof. Neither defence of the defendant nor averments made int he application have to be given any weightage. Plaint has to be read as a whole together with the documents filed by the plaintiff." CS (COMM)100/24 M/s Rysa Infratech Pvt. Ltd. Vs. The Chief Engineer Pune Zone And Anr Page no. 8 of 10 -- 8 of 10 -- 23. Their Lordship of Supreme Court in case of Ramisetty Venkatanna & Anr. Vs. Nasyam Jamal Saheb & Ors. in CIVIL APPEAL NO. 2717 OF 2023 was pleased to observe as under:- “ Now, so far as the reliance placed on the decision of the Privy Council referred to hereinabove and on the decision of this Court in the case of Subhaga (supra) are concerned, there cannot be any dispute with respect to the proposition of law laid down in the aforesaid two decisions. However, the question is the suit being barred by limitation and the illusory cause of action. Now so far as the reliance placed upon the decision of this Court in the case of Nusli Neville Wadia (supra) is concerned, again there cannot be any dispute with respect to the proposition of law laid down by this Court that while deciding the application under Order VII Rule XI, mainly the averments in the plaint only are required to be considered and not the averments in the written statement. However, on considering the averments in the plaint as they are, we are of the opinion that the plaint is ought to have been rejected being vexatious, illusory cause of action and barred by limitation and it is a clear case of clever drafting. In view of the above and for the reasons stated, the impugned judgment and order passed by the High Court and that of the learned Trial Court rejecting the application under Order VII Rule XI are unsustainable and the same deserve to be quashed and set aside and are accordingly, quashed and set aside. Consequently, the application submitted by the appellants – original defendant Nos. 9 and 10 to reject the plaint in exercise of powers under Order VII Rule XI(a) and (d) of the CPC is hereby allowed and consequently, the plaint of Civil Suit (O.S.) No. 35/2014 is ordered to be rejected. Present appeal is accordingly allowed. No costs”. 24. Coming to the case in hand, since the plaintiff has averred and explained about the details of cause of action arose to it to file the present case against the defendant, so, taking into consideration the averments made by the plaintiff in it’s plaint, this court is of the considered opinion that since from the facts averred in the plaint, the plaintiff is having cause of action to file the present suit against the defendant no.2 and since from the law laid down by their lordships of High Court and Hon’ble Supreme Court, in the abovesaid judgments, it is clear that at the time of the disposal of the application under Order 7 rule 11 of CPC, only the averments made in the plaint are required to be looked into and from the averments made in CS (COMM)100/24 M/s Rysa Infratech Pvt. Ltd. Vs. The Chief Engineer Pune Zone And Anr Page no. 9 of 10 -- 9 of 10 -- the plaint, it is clear that plaintiff has valid cause of action to file the present suit against the defendant no.2. So, the application filed by the defendant no.2 under Order 7 rule 11 r/w Section 151 of CPC is hereby dismissed, being devoid of merit. (PAWAN KUMAR MATTO) DISTRICT JUDGE (COMMERCIAL COURT)-04, SHAHDARA, KKD, Delhi/25.11.2024 CS (COMM)100/24 M/s Rysa Infratech Pvt. Ltd. Vs. The Chief Engineer Pune Zone And Anr Page no. 10 of 10 -- 10 of 10 --