Skip to main content
Court Order

Order 1

CNR DLNW03001709202523 Sept 2025
Back to Case

Full Order Text

Order 1 · 23 Sept 2025 · CNR DLNW030017092025

Order Details: COPY OF JUDICIAL PROCEEDINGS
Pdf Text: pg. no. 1/2
CS SCJ 1150/25
NIRMAL GUPTA Vs. GOVT OF NCT OF DELHI
23.09.2025
Fresh suit received from filing counter. It be checked and
registered as per rules.
Present: Son of the plaintiff in person.
Mr. Shikhar Mittal and Mr. Shantanu Awasthi, Ld.
Counsels for the plaintiff.
Heard. Record perused.
Let summons be issued to the defendants on filing of
PF / RC / through all prescribed modes returnable for NDOH. PF
be deposited within 2 working days from today.
Further, Ld. Counsel for the plaintiff has also sought
interim protection from demolition of the suit property without due
process. In this regard, Ld. Counsel has filed on record copies of
such similar notices issued to people having adjoining shops as
well and informed the court that such people’s properties were
demolished in a hush and plaintiff also apprehends that in a like
manner, such action qua his property may also be taken, without
being accorded a fair hearing.
Arguments heard.
The plaintiff has filed sale deed qua the suit property
on record in his name. Further, the impugned notice dated
17.09.2025 as well is seen to be rather peculiar. This is so since no
provision has been cited therein as to under which it has been
issued or the action proposed is sought to be taken. The plaintiff at
its own end, has shown his bonafides, by filing on record copy of
reply filed by him to notice issued, bearing the stamp of receiving
as well. Taking the totality of circumstances into consideration
-- 1 of 2 --
pg. no. 2/2
therefore, it is seen that if despite replying to the notice, the
demolition takes place irrespective without due process, the
purpose of filing the suit itself shall be rendered infructuous.
Fairness demands therefore that plaintiff be afforded protection in
the interregnum, at least till NDOH.
In view of the above, the authorities
concerned/defendants are restrained from taking any coercive /
demolition action in terms of notice dated 17.09.2025 issued by
PWD with regards suit property – shop situated at plot no. 1/5,
Shalimar Bagh, Village Singalpur, Delhi-110088 belonging to the
plaintiff till NDOH.
Above order be treated as one under Order 39 Rule 1
& 2 CPC and be adhered to accordingly.
Compliance be made by the plaintiff within the meaning
of Order 39 Rule 3 CPC.
Copy of the order be given dasti.
Re-list on 10.10.2025.
(Gaurav Sharma)
JSCC-cum-ASCJ-cum-Guardian Judge
North West/Rohini Courts/Delhi
23.09.2025
-- 2 of 2 --