Order 5

CNR DLNW03001216202517 Oct 2025
Back to Case

Full Order Text

Order 5 · 17 Oct 2025 · CNR DLNW030012162025

Order Details: COPY OF JUDICIAL PROCEEDINGS
Pdf Text: CS SCJ 824/25
MR SWARUP PAUL
Vs.
MR ATAM PRAKASH TUTEJSA AND ORS
17.10.2025
Ld. PO is on first half leave.
Present: Plaintiff in person alongwith Ld. Counsel Mr. Sunil
Dahiya.
At request of Ld. Counsel for the plaintiff, kept
awaited at 02:00 PM.
(Reader)
17.10.2025
AT 02:20 PM
Present: Plaintiff in person alongwith Ld. Counsel Mr. Sunil
Dahiya.
Mr. Harshit Jain, Ld. Counsel for the defendants no. 1
& 2 through VC.
Ld. Counsel for the plaintiff states that he may be
allowed to withdraw the application under O 6 R 17 CPC and the
amended suit filed therewith.
In view of the above, application under O 6 R 17 CPC
stands withdrawn.
A fresh application under O 6 R 17 CPC alongwith an
application under O 1 R 10 CPC has been filed alongwith the
amended suit. Taken on record. Copy be supplied.
Let reply be filed by NDOH with an advance copy to
the opposing side at least a week prior thereto.
Notice of the application under O 1 R 10 CPC be
issued on filing of PF returnable for NDOH.
-1/2-
-- 1 of 2 --
Ld. Counsel for the plaintiff has pressed for the urgent
application filed U/s 151 CPC for restoration of electricity. Even on
LDOH, submissions were made in that regard. Considering the
nature of urgency and the festive period being around, it is put forth
to the Ld. Counsel for the defendants appearing through VC as to
whether he is agreeable to a scenario where for the time being, the
plaintiff clears all the electricity dues qua the suit property subject
to his rights to be pressed / adjudicated going forward as to the
actual amount payable by him and by the defendants and whether
there is any objection to such restoration on such terms. Ld.
Counsel for the defendants states that no objection to such an
understanding is there.
In view of the above, the application U/s 151 CPC is
hereby Allowed to the extent that subject to payment of all
electricity bill dues by the plaintiff, pending as on date today for the
suit property where the plaintiff is the tenant (Plot No. 4, First
Floor, Pocket 15A, Sector 24, Rohini, Delhi-110085, admeasuring
3000 sq. ft. approx. – entire portion of First Floor and a hall on the
Second Floor), defendant no. 3 / TPDDL to restore electricity
connection thereof without delay. The defendants no. 1 & 2 shall
not raise any objection in that regard and if required, shall cooperate
for restoration of electricity connection.
Application disposed in the above-mentioned terms.
Re-list on 03.02.2026.
Copy of this order be given dasti.
(Gaurav Sharma)
JSCC-cum-ASCJ-cum-Guardian Judge
North West/Rohini Courts/Delhi
17.10.2025