Full Order Text
Final Order 4 · 12 Oct 2026 · CNR DLNW010119862026
Order Details: COPY OF ORDER Pdf Text: IN THE COURT OF SH. MANISH GUPTA, LD. DISTRICT JUDGE (COMMERCIAL COURT)-02 NORTH-WEST/ROHINI COURTS, DELHI In the matter :- OMP (I) (COMM.) 649/2026 DLNW010119862026 1. BIKANERVALA PVT LTD Through its Authorised Representative Sh. Parvinder Kumar Having registered office at A-28, Lawrence Road, Industrial Area, Delhi-110035. ………… Petitioner no. 1. 2. M/s Tough 2 Enough Fitness and Spa Pvt. Ltd. Through its Authorised Representative Mr. Wasim Saifi Having registered office at H. No. 12, Park Drive, Malibu Town, Sector-47, Gurgaon, Haryana-122001. ………… Petitioner no. 2. VS. M/S ADVANCE INDIA PROJECTS LTD. Through its Director / AR / Principal Officer Having registered office at AIPL Business Club 5th Floor, Golf Course Extension Road, Sector-62, Gurgaon, Haryana-122001 …….…. Respondent 12.10.2026 Order on the Petition u/s 9 of Arbitration & Conciliation Act, 1996 filed on behalf of Petitioners. 1. This is a petition seeking interim measures u/s 9 of the Arbitration & Bikanervala Pvt Ltd & Anr. Vs. M/S Advance India Projects Ltd. Page 1 of 19 -- 1 of 19 -- Conciliation Act, 1996. 2. The relevant facts of the case as mentioned in the petition are that the Petitioner No. 1 BIKANERVALA PRIVATE LIMITED, is a company incorporated under the provisions of the Companies Act, 2013, having its registered office at A-28, Lawrence Road Industrial Area, Delhi-110035. The Petitioner No. 1 is engaged, inter alia, in the business of manufacturing, selling and marketing of food products and in operating and managing restaurant(s)/food outlet(s) including through franchise(s) under the trade names "BIKANERVALA" and "ΒΙΚΑΝΟ". 3. That in terms of order dated 21.07.2023 passed by the Hon'ble NCLT Delhi in CP (CAA) No. 34/230/232/ND/2022 the domestic restaurant business of M/s. Bikanervala Foods Pvt. Ltd. has been transferred to M/s. Bikanervala Pvt. Ltd. i.e. the petitioner no. 1 herein. As per scheme of arrangement and order passed by Hon'ble NCLT, Delhi, all contracts of said Bikanervala Foods Pvt. Ltd., which were subsisting or having effect immediately before the 'effective date' stand transferred to and vested in "Bikanervala Pvt. Ltd." 4. That the Petitioner No. 2 M/s. Tough 2 Enough Fitness and Spa Private Limited, is also a Private Limited company incorporated under the provisions of the Companies Act, 2013, having its registered office at H. No. 12, Park Drive Malibu Town, Sector-47, Gurgaon, Haryana-122001. The petitioner no. 2 is engaged in wellness, and hospitality related Bikanervala Pvt Ltd & Anr. Vs. M/S Advance India Projects Ltd. Page 2 of 19 -- 2 of 19 -- services/business. 5. That the Petitioner No.2 is the authorized franchisee operating the BIKANERVALA outlet from the subject premises under the Franchise arrangement executed between the Parties. 6. That the respondent M/s. Advance India Projects Limited is a Public Limited company incorporated under the provisions of the Companies Act, 2013, having its registered office at AIPL Business Club, Fifth Floor, Golf Course Extension Road, Sector 62, Gurgaon, Haryana 122101. The respondent no.2 is engaged in real estate business. 7. That a Lease Agreement dated 09.01.2018 (hereinafter referred to as the "Lease Agreement/LA") was originally executed between Bikanervala Foods Private Limited, as the LESSEE, and the Respondent, Advance India Projects Limited, as the LESSOR, in respect of the commercial premises situated at The Celebration Bazaar, Khanna, Punjab, comprising Shop Nos. GF-44 & GF-45 part of departmental store and extension of departmental store at the Ground Floor and Shop Nos. AG-28A & 30A at the Lower Ground Floor, admeasuring approximately 10,768 sq. ft. super area and approximately 7,000 sq. ft. covered area (hereinafter referred to as the "Demised Premises"). Under the Lease Agreement, the Respondent granted a lease for a period of twenty (20) years commencing from the Rent Commencement Date, with a three-year lock-in period. 8. That as stated above the petitioner no. 1 stepped into the shoes of Bikanervala Pvt Ltd & Anr. Vs. M/S Advance India Projects Ltd. Page 3 of 19 -- 3 of 19 -- Bikanervala Foods Private Limited post the aforesaid approval of scheme of arrangement. Moreover, the Respondent's own contemporaneous conduct further evidences its recognition of the Petitioner No.1 in relation to the Demised Premises. In October 2023, pursuant to the demerger of the domestic restaurant business, the Petitioner No. 1 informed the Respondent, vide e-mail communications dated 14.10.2023 and 18.10.2023, regarding the change in the corporate structure and the effectiveness of the new entity, Bikanervala Private Limited, with effect from 01.09.2023, and furnished the new GST and PAN particulars, while specifically requesting the Respondent to issue the rental invoices in the name of Bikanervala Private Limited with effect from September 2023. The Respondent thereafter raised rental invoices in the name of Bikanervala Private Limited in respect of the Demised Premises and continued to receive rental payments from the Petitioner No. 1. 9. That the Petitioner No.2 invested substantial amount of more than two crore towards setting up, fitting out, equipping and operating the BIKANERVALA outlet at the Demised Premises, besides incurring continuing expenditure towards manpower, inventory, licences, maintenance and day-to-day operations. The said investment and continuing business operations have been undertaken on the basis of the subsisting contractual arrangement of twenty (20) years governing the Demised Premises and the franchise relationship between the Petitioners. Petitioner No.2 is impleaded as the franchisee/operating entity whose possession, business, stock, equipment, investment and contractual Bikanervala Pvt Ltd & Anr. Vs. M/S Advance India Projects Ltd. Page 4 of 19 -- 4 of 19 -- interests are directly affected by the Respondent's acts. The continued availability of electricity and peaceful possession of the Demised Premises is indispensable for the functioning of the outlet. 10. That the present petition is principally founded upon the Lease Agreement dated 09.01.2018 and the arbitration agreement contained therein. The Lease Agreement contains express covenants protecting the Petitioners' rights: (a) Essential Utilities: The Respondent expressly assured and warranted that the Demised Premises would have adequate arrangements for power and electricity, 100% power back-up, water and other specified utilities and, significantly, guaranteed the continued availability of the Essential Utilities to the Lessee throughout the term of the Agreement. (b) Quiet and Peaceful Enjoyment: Clause 12 records that, upon payment of rent and observance of the terms of the LA, the LESSEE shall peacefully possess and enjoy the Demised Premises without disturbance or hindrance from the LESSORS or any person(s). The indemnity covenant further records the Respondent's obligation to ensure that the LESSEE shall peacefully hold, possess and enjoy the Demised Premises during the full term of the Lease without interruption, disturbance or demands by the LESSORS or persons acting on their behalf. (c) Operation via Franchisee: Clause 15 of the Lease Agreement expressly reserves to the LESSEE the right to manage and operate the Demised Premises either on its own or through its subsidiary company, sister concern or third party by granting Franchisee Rights, and expressly provides that the same shall not be subjected to any objection or Bikanervala Pvt Ltd & Anr. Vs. M/S Advance India Projects Ltd. Page 5 of 19 -- 5 of 19 -- interference by the LESSOR, subject to the permitted use and brand name stipulated under the Lease Agreement. The Lease Agreement further permits sub-letting for the specific purpose of operating the BIKANERVALA Sweet Shop cum Restaurant. The operation of the BIKANERVALA outlet by Petitioner No.2 pursuant to the Franchise Agreement is therefore expressly contemplated and protected by the Lease Agreement itself. 11. That the Lease Agreement contains a specific contractual mechanism governing termination by the LESSOR. Clause 11 thereof is expressly titled "TERMINATION OF LEASE OF THE DEMISED PREMISES BY THE LESSORS. 12. That the Lease Agreement does not contain any express provision conferring upon the Respondent an unrestricted or without-cause right to terminate the Lease and that too merely on the ground that, according to the Respondent, the entire Demised Premises are not being commercially utilised. In particular, the Lease Agreement does not expressly stipulate that simultaneous commercial operation of both the Ground Floor and Lower Ground Floor is a condition precedent for continuation of the Lease or that alleged under-utilisation of any portion of the Demised Premises, by itself, confers an independent right of termination upon the LESSOR. 13. That the Petitioners have at all material times continued to make payments towards the rent/revenue share and other amounts payable under Bikanervala Pvt Ltd & Anr. Vs. M/S Advance India Projects Ltd. Page 6 of 19 -- 6 of 19 -- the Lease Agreement. It is further material that, just two-three days prior to the date of filing of the present petition, the Respondent has raised rental invoices to the Petitioner for the months of August 2026 and September 2026. 14. That despite the Petitioners' compliance with the contractual arrangement, the Respondent issued a Defect Cure Notice dated 26.06.2026 alleging, inter alia, that the Petitioners had kept the Lower Ground Floor substantially non-operational and under-utilized, and alleging certain operational and commercial deficiencies and that the continued non-operation at the Lower Ground Floor has deprived the respondent of the anticipated commercial benefits under the Lease deed. 15. That thereafter, the Respondent issued a Notice dated 21.08.2026 for Termination of the Lease Deed, received on 27.08.2026, addressed to Bikanervala Foods Private Limited, purporting to terminate the Lease Agreement and directing vacation of the entire Demised Premises within thirty (30) days from receipt thereof. 16. That the purported termination is founded solely upon alleged non- utilisation/under-utilisation of the Lower Ground Floor and alleged operational/commercial deficiencies. Significantly, the Respondent has not alleged in its Defect Cure Notice or Termination Notice that the rent remained unpaid for three consecutive months, nor has the Respondent invoked Clause 11 on the ground of three consecutive months non- Bikanervala Pvt Ltd & Anr. Vs. M/S Advance India Projects Ltd. Page 7 of 19 -- 7 of 19 -- payment of rent. 17. That, thereafter, while the Petitioners continued in possession of the Demised Premises and while the dispute regarding the validity of the purported termination remained unresolved, the Respondent, in furtherance of its extraneous and evil designs, caused the electricity supply to the Demised Premises to be disconnected on 27.09.2026 at approximately 11:00 A.M., without any prior written notice or order of any competent Court. The disconnection completely disrupted and brought to a standstill the operations of the BIKANERVALA outlet being operated by Petitioner No. 2. 18. That immediately upon the electricity being disconnected, Petitioner No.2 sent an e-mail dated 27.09.2026 to the management of the Respondent requesting immediate restoration of the electricity and recording that the sudden disconnection had caused heavy losses and completely disrupted the outlet operations. Thereafter, Petitioner No.1, through its authorised representative, sent a further e-mail dated 28.09.2026 to the Respondent and its representatives demanding immediate restoration of electricity and calling upon the Respondent to cease interference with the Petitioners peaceful possession and business operations. 19. That the electricity disconnection has caused immediate and continuing damage to the Petitioners' business. The Demised Premises contain highly perishable food items, including frozen goods, raw Bikanervala Pvt Ltd & Anr. Vs. M/S Advance India Projects Ltd. Page 8 of 19 -- 8 of 19 -- materials and other the Petitioners have inventory requiring refrigeration, and contemporaneously informed the Respondent that stock of substantive value of INR. 10,00,000/- was at risk of spoilage and deterioration on account of the electricity disconnection. 20. That Petitioner No.2, through its authorised representative, constrained to approach the local police authorities on 29.09.2026 in relation to the disconnection of electricity and the apprehended interference with the outlet and goods lying therein. 21. That a dispute has accordingly arisen between the parties in relation to the subsistence, validity and enforceability of the Agreement, the legality of the Respondent's purported termination, the Petitioners' right to peaceful possession and enjoyment, and the Respondent's contractual obligation to maintain Essential Utilities. The said dispute squarely arises out of and in connection with the Agreement and is referable to arbitration under Clause 24 of the LA. 22. That Clause 24 of the Agreement provides for amicable resolution in the first instance and, upon failure, reference of unresolved disputes to arbitration in accordance with the Arbitration and Conciliation Act, 1996. The clause expressly provides that the seat of arbitration shall be at New Delhi. 23. That the Petitioners manifestly intend to invoke the arbitration Bikanervala Pvt Ltd & Anr. Vs. M/S Advance India Projects Ltd. Page 9 of 19 -- 9 of 19 -- agreement contained in Clause 24 of the Lease Agreement and to have the disputes arising therefrom adjudicated by the competent arbitral tribunal. The present petition is being filed as an urgent interim measure in view of the continuing electricity disconnection and the immediate threat to peaceful possession. The Petitioners undertake to commence arbitral proceedings in accordance with the Arbitration and Conciliation Act, 1996. 24. The above paragraphs reflects the averments of the petitioners as mentioned in the petition under consideration. The petitioners have prayed for the following reliefs as per the prayer clause of the petition:- a. To pass an ad-interim and/or interim order pending the commencement and during the arbitration proceedings, directing the Respondent, its directors, officers, agents, representatives, employees and all persons acting on its behalf to forthwith restore and maintain the electricity/power supply to the Demised Premises comprising Shop Nos. GF-44 & GF-45 and LGF-AG-28A & 30A, The Celebration Bazaar, Khanna, Ludhiana, Punjab; b. To pass an ad-interim and/or interim injunction pending the commencement and during the arbitration proceedings, restraining the Respondent, its directors, officers, agents, representatives, employees, contractors, facility managers and all persons acting on its behalf from interfering with the Petitioners' peaceful possession, occupation, access, use and enjoyment of the Demised Premises, including by locking, sealing, Bikanervala Pvt Ltd & Anr. Vs. M/S Advance India Projects Ltd. Page 10 of 19 -- 10 of 19 -- obstructing ingress or egress, dispossessing the Petitioners, removing or interfering with their goods, stock, equipment, fixtures or installations, disconnecting any essential utility or otherwise taking any coercive measure for obtaining possession, except in accordance with the express terms of the Lease Agreement and due process of law, pending adjudication of the disputes by the arbitral tribunal; c. To pass an ad-interim and/or interim order pending the commencement and during the arbitration proceedings, restraining the Respondent from creating any third-party right, interest, tenancy, licence or possession in respect of the Demised Premises in derogation of or inconsistent with the subsisting contractual rights of Petitioner No.1 under the Lease Agreement, pending adjudication of the disputes by the arbitral tribunal. 25. The petition is duly supported by the Statement of truth. The petition is signed on each page by the petitioners. The copy of the relevant documents relied upon by the petitioners is also filed with the petition. 26. It is relevant to note here that on 10.10.2026 (Saturday), the Ld. Counsel for petitioners addressed arguments and prayed for passing ex- parte ad-interim order as per the prayer clause of the petition. The matter was then put up for passing appropriate orders for today i.e. 12.10.2026. The notice of the petition was not issued to the respondent at that time. However, the Ld. Counsel for respondent, namely, Sh. Siddharth Joshi, Bikanervala Pvt Ltd & Anr. Vs. M/S Advance India Projects Ltd. Page 11 of 19 -- 11 of 19 -- Advocate appeared today before the court of his own in this matter and submitted that through online portal, the respondent came to know about pendency of this petition. Ld. Counsel for respondent prayed for providing the copy of petition. Same was supplied to him. Thereafter, pass over was sought by him. Subsequently, after pass over, Ld. Counsels for both the parties addressed arguments. The documents are not in dispute. The Ld. Counsel for respondent argued that this court is not having territorial jurisdiction to entertain and try this petition. Ld. Counsel for respondent highlighted Clause 24 of the Lease Agreement dated 09.01.2018. For the sake of convenience, the said Clause 24 is reproduced below:- a. If a dispute arises in relation to, touching, arising out of, or in connection with this Lease Agreement, shall be resolved amicably at the first instance whereby referring the same to Directors of both the parties. The final outcome of the same whether resolved or unresolved, as the case may be, shall be recorded in writing. Unresolved disputes, controversies, contests, disputes, if any, shall be submitted to arbitration within 30 days from the date of failure to resolve the dispute or difference. The Arbitration shall be conducted in accordance with the Provisions of the Arbitration and Conciliation Act, 1996 along with the rules framed there under and any amendments thereto by a sole arbitrator, duly appointed by the both parties mutually. The arbitration shall be conducted in English. The decision/ award of the arbitrator shall be final/ conclusive and binding on the parties. The seat of arbitration shall be at New Delhi. The Arbitrator's Bikanervala Pvt Ltd & Anr. Vs. M/S Advance India Projects Ltd. Page 12 of 19 -- 12 of 19 -- fee shall be borne by all the parties equally. b. Notwithstanding anything contained in clause 24 (a) mentioned herein above, this Lease Agreement shall not preclude either party from seeking, temporary, provisional, or injunctive relief from courts having jurisdiction over this Lease Agreement. This Lease Agreement shall be governed by the laws of India and Courts at Khanna shall have exclusive jurisdiction in all matters arising out of this Lease Agreement. 27. Ld. Counsel for respondent submitted that as per the said Clause, the Courts at Khanna, Punjab are having exclusive jurisdiction over this matter. A query was also put to Ld. Counsel for respondent by the court as to which court is competent according to the respondent, to appoint the arbitrator, and, the Ld. Counsel replied that the courts at Khanna, Punjab are competent to appoint the arbitrator. On the other hand, Ld. Counsel for petitioners argued that since the seat of arbitration shall be at New Delhi as per Clause 24, therefore, the courts at New Delhi only shall be having the exclusive jurisdiction in all the matters arising out of the Lease Agreement. Ld. Counsel for petitioners submitted that seat shall prevail over the exclusive jurisdiction Clause meaning thereby that New Delhi Courts shall prevail over Khanna Courts. There is no dispute regarding the contents of the said arbitration clause. However, the dispute is only regarding its interpretation. Clause 11 of the Lease Agreement provides for termination of lease of the demised premises by the Lessor. The non payment of rent for a period of three consecutive months is the ground for termination of Bikanervala Pvt Ltd & Anr. Vs. M/S Advance India Projects Ltd. Page 13 of 19 -- 13 of 19 -- lease. The case in hand is not regarding non payment of rent. Ld. Counsel for respondent also argued that this court is also not having pecuniary jurisdiction to entertain this case as the term of lease is twenty years and in case, the rent for twenty years period is calculated then it shall be more than Rs. 2 crores, which is the pecuniary limit of this court. On the other hand, Ld. Counsel for petitioners submitted that the petitioners have estimated the loss to the tune of Rs. 10,00,000/- (Rupees ten lacs) only at the time of filing this petition and accordingly, the petition is within pecuniary jurisdiction of this court. 28. The Ld. Counsel for respondent also argued that the petitioners have not challenged the validity of termination of lease in this petition and therefore, the petition is not maintainable. The Ld. Counsel for petitioners submitted that the petitioners have approached this court only for limited purpose of seeking interim relief from the court and the remaining dispute shall be adjudicated by the Ld. Arbitrator after commencement of the proceedings consequent to appointment of the arbitrator. 29. During arguments, a query was also put to Ld. Counsel for the respondent regarding the possession of the demised premises and Ld. Counsel for respondent replied that as on date, the possession of the said premises is with the petitioners. 30. After concluding arguments, Ld. Counsel for respondent also filed written submissions. I have considered the same also. Both the parties have Bikanervala Pvt Ltd & Anr. Vs. M/S Advance India Projects Ltd. Page 14 of 19 -- 14 of 19 -- also relied upon certain judgments of Hon’ble Superior Courts. The same have also been perused. The respondent has also referred to termination notice dated 21.08.2026 under the Lease Agreement dated 09.01.2018. The respondent has also referred to defect cure notice dated 26.06.2026 in the written submissions. Ld. Counsel for petitioners relied upon the judgment titled as “Devyani International Limited VS. Siddhi Vinayak Builders and Developers, decided on 27.09.2017” passed by the Hon’ble High Court of Delhi. The said judgment also deals with similar issue under consideration. It is in support of the case of the petitioners. The other judgment relied upon by Ld. Counsel for petitioners is titled as “BGS SGS SOMA JV Vs. NHPC Limited, decided on 10.12.2019”, by the Hon’ble Supreme Court of India. Ld. Counsel for petitioners highlighted para no. 46, 47 and 48 of the said judgment. It also supports the case of the petitioners. The other judgment relied upon by Ld. Counsel for petitioners is titled as “Yasshdeep Builders LLP Vs. Sushil Kumar Singh & Ors, decided on 01.03.2024” by the Hon’ble High Court of Delhi. Ld. Counsel for petitioners highlighted para no. 12, 26, 27, 43, 44, 45, 46, 47, 48 of the said judgment. It also supports the case of the petitioners. 31. Ld. Counsel for petitioners submitted that the last paid rent was on 26.07.2026 in the sum of Rs. 2,94,840/- relevant entry of bank statement was highlighted. In the petition, it is mentioned that just two-three days prior to the date of filing of the present petition, the Respondent has raised rental invoices to the Petitioner for the months of August 2026 and September 2026. The petitioners are obliged to pay the same timely. The Bikanervala Pvt Ltd & Anr. Vs. M/S Advance India Projects Ltd. Page 15 of 19 -- 15 of 19 -- copy of Franchise Agreement dated 14.11.2017 is also on record, which is between Bikanervala Foods Private Limited and Tough 2 Enough Fitness and SPA Private Limited and Advance India Projects Limited. Copy of Lease Agreement dated 09.01.2018 is also on record. Clause 3.3 of the Lease Agreement dated 09.01.2018 deals with electricity / power load in the demised premises. The copy of defect cure notice dated 26.06.2026 is also on record. In para no. 4 of the said notice, it is mentioned that the addressee i.e. Bikanervala Foods Private Limited has operated only from the ground floor while keeping the lower ground floor substantially non operational and underutilised. 32. The respondent has also relied upon some citations as reflected in the written submissions. The said judgments are not squarely attracted to the facts of this case in so far as the contentions raised on behalf of respondent are concerned. 33. Moreover, the recent judgment of the Hon’ble High Court of Delhi titled as “M/s KLA Const. Technologies Pvt. Ltd. Vs. M/s Gulshan Homz Pvt. Ltd.” (2025: DHC: 4217), decided on 14.05.2025 is also relevant, which also supports the case of the petitioners in terms of territorial jurisdiction. Para no. 20 and 21 of the said judgment are relevant, which are reproduced as under:- “20. Moreover, this Court, in Devyani International Ltd. v. Siddhivinayak Builders and Developers, therein held that when Clause 11 of the Agreement designated New Delhi as the seat of arbitration, but Clause 12 conferred Bikanervala Pvt Ltd & Anr. Vs. M/S Advance India Projects Ltd. Page 16 of 19 -- 16 of 19 -- exclusive jurisdiction on the Courts at Mumbai, primacy must be given to the seat. The Court held that once the seat has been designated, only the Courts at the seat would have jurisdiction to entertain applications arising out of the arbitration Agreement. Relevant paragraphs affirming the aforesaid is reproduced below: “8. In view of the Clause 11.1 above, it is obvious that the seat of arbitration is Delhi. In this context reference may be had to the judgment of the Supreme Court in Indus Mobile Distribution Private Ltd. v. Datawind Innovations Pvt. Ltd., (2017) 7 SCC 678, the Supreme Court held as follows: “19. A conspectus of all the aforesaid provisions shows that the moment the seat is designated, it is akin to an exclusive jurisdiction Clause. On the facts of the present case, it is clear that the seat of arbitration is Mumbai and Clause 19 further makes it clear that jurisdiction exclusively vests in the Mumbai courts. Under the Law of Arbitration, unlike the Code of Civil Procedure which applies to suits filed in courts, a reference to “seat” is a concept by which a neutral venue can be chosen by the parties to an arbitration Clause. The neutral venue may not in the classical sense have jurisdiction-that is, no part of the cause of action may have arisen at the neutral venue and neither would any of the provisions of Section 16 to 21 of the Code of Civil Procedure be attracted. In arbitration law however, as has been held above, the moment “seat” is determined, the fact that the seat is at Mumbai would vest Mumbai courts with exclusive jurisdiction for purposes of regulating arbitral proceedings arising out of the agreement between the parties.” 9. In the light of the above legal position, it is manifest that the Agreement records that the seat of arbitration shall be Delhi. In view of the above legal position the courts at Delhi would have exclusive jurisdiction to adjudicate the dispute between the parties. The reliance of the learned counsel for the respondent on Clause 12 of the agreement is misplaced due to the clear terminology used in Clause 11.1 of the agreement, i.e. “seat of arbitration shall be Delhi.”” 21. Similarly, in NJ Construction v. Ayursundra Health Care (P) Ltd., although the Agreement therein conferred exclusive jurisdiction on the Courts at Guwahati, the seat of arbitration was New Delhi. This Court ruled that only the Courts at the seat New Delhi, would have jurisdiction, rejecting the Bikanervala Pvt Ltd & Anr. Vs. M/S Advance India Projects Ltd. Page 17 of 19 -- 17 of 19 -- claim of jurisdiction by Courts at Guwahati. Several other coordinate Benches of this Court have consistently followed this line of reasoning, reaffirming that the designation of a seat of arbitration carries with it exclusive supervisory jurisdiction, overriding any contrary Clause on Court s ‟ jurisdiction.” 34. In view of totality of the facts and circumstances of the case and also, in view of the judgments of Hon’ble Superior Courts relied upon by the petitioners, it is clear that this court is having territorial jurisdiction to entertain and decided this petition. The seat of the arbitration shall be at New Delhi, which will prevail over the exclusive jurisdiction Clause regarding Khanna Courts of Punjab. Moreover, the petitioners are the dominus litus and the specified value of the petition is Rs. 10,00,000/- (Rupees Ten Lakhs). This court is having pecuniary jurisdiction also to entertain and decide this petition. The validity of termination notice shall be adjudicated by the Ld. Arbitrator as and when appointed. The petitioners are dealing in perishable goods / food items. The petitioners shall suffer irreparable loss or injury in case, the electricity to the demised premises is not restored immediately by the respondent. The balance of convenience also lies in favour of petitioners. There is no other equally efficacious remedy available with the petitioners. The defect cure notice dated 26.06.2026 talks about underutilization of the lower ground floor of the demised premises. It does not talk about non payment of rent by the petitioners for consecutive three months period. The petitioners are able to show a prima facie case in their favour. Hence, in view of the overall facts and circumstances of the case, the petitioners are entitled for interim relief in their favour and against the respondent under the provisions of Section 9 Bikanervala Pvt Ltd & Anr. Vs. M/S Advance India Projects Ltd. Page 18 of 19 -- 18 of 19 -- of the Arbitration & Conciliation Act, 1996. 35. Accordingly, the Respondent, its directors, officers, agents, representatives, employees and all persons acting on its behalf is / are directed to forthwith restore and maintain the electricity/power supply to the Demised Premises comprising Shop Nos. GF-44 & GF-45 and LGF- AG-28A & 30A, The Celebration Bazaar, Khanna, Ludhiana, Punjab and hereby restrained from interfering with the Petitioners' peaceful use, occupation and enjoyment of the Demised Premises, and further hereby restrained from creating any third-party right, interest, tenancy, licence or possession in respect of the Demised Premises, except in accordance with due process of law. Needless to mention here that the parties to this petition shall do the needful strictly in accordance with Sub-Section (2) of Section 9 of the Arbitration & Conciliation Act, 1996. Ordered accordingly. The present petition u/s 9 of Arbitration & Conciliation Act, 1996 stands disposed off accordingly. File be consigned to record room after completing necessary formalities. Copy of this order be given dasti to both the sides. Passed and announced in the (Manish Gupta) open Court on 12.10.2026 District Judge (Commercial Court)-02 North-West/Rohini Courts Bikanervala Pvt Ltd & Anr. Vs. M/S Advance India Projects Ltd. Page 19 of 19 -- 19 of 19 --