07.04.2025
Present: None for state.
Sh. Satish Kumar, A/R of the complainant company
Ms. Mansha, Assistant Manager (Legal) of the
complainant /TPDDL.
Accused in person with counsel Sh. Tarun.
Fresh vakalatnama along with an application seeking bail is
filed by accused.
Submissions of Ld. Counsel for accused heard.
The present case is U/S 135 r/w Section 150 of the
Electricity Act. The case is based upon the documentary evidence. Trial
of this case will take its own time. Considering all these facts, the
accused is admitted on bail on furnishing the personal bond and the
surety bond of Rs.20,000/-.
Bail bond has been furnished, same is considered and
accepted.
The documents have been supplied to Ld. Counsel for
accused and he has gone through the documents. Same are complete.
Submissions on framing of notice heard.
It is submitted by Ld. Counsel for accused that accused has
been falsely implicated in the instant matter and no offence is made out
against him.
-- 1 of 2 --
-2-
Per contra, it is submitted by complainant company that
prima faice offence under Section 135 r/w Section 150 of Electricity Act
is made out against the accused as the sufficient material is on record
against the accused.
As per Section 154 (3) of the Electricity Act, 2003, the
special court may, notwithstanding anything contained in sub-section (1)
of section 260 or section 262 of the Code of Criminal Procedure, 1973,
try the offence referred to in (sections 135 to 140 and section 150) in a
summary way in accordance with the procedure prescribed in the said
Code and the provisions of section 263 to 265 of the said Code shall, so
far as may be, apply to such trial.
Accordingly, notice U/S 135 r/w Section 151 Electricity
Act is framed qua accused to which he pleaded not guilty and claimed
trial.
Be put up for PE on 05.06.2025.
Let witnesses be summoned for the NDOH.
(PRASHANT KUMAR)
ASJ (Electricity)/(N-W)
Rohini Courts, Delhi
07.04.2025
-- 2 of 2 --