Order Details: COPY OF JUDICIAL PROCEEDINGS
Pdf Text: Arbitration No.:482/2025
Sumit Chugh Vs. Soni Infratech Pvt. Ltd.
13.08.2025
Fresh petition u/S 9 of Arbitration and Conciliation Act, 1996
received by assignment.
It be checked and registered.
Present : Mr. Piyush Chhabra, Mr. Anand Beniwal & Ms.
Riya Srivastava, Ld. Counsels for the petitioner.
Fresh petition u/S 9 of Arbitration and Conciliation
Act is filed alongwith the application for urgent hearing. It is
submitted by ld. Counsel for petitioner that one residential unit
No. T-2 0802 in ORION Galaxy at Sector 68, Gurgaon was
bought by applicant. It is further stated that respondent No.1 is
the private Limited Company operated within the Real Estate and
Infrastructure Development Sector and the respondent No.2 to 7
are the officials of respondent No.1. It is further stated that in the
year 2010 applicant was induced by the respondents to book the
above mentioned unit. However, despite receiving the substantial
amount out of the total payable amount, the respondent miserably
failed to complete the same. It is further stated that insolvency
proceedings was initiated against the respondent company and
consequently Interim Resolution Professional (IRP) was
appointed vide order dated 22.11.2019 passed by Hon’ble NCLT.
It is further stated that appeal was preferred against the order of
NCLT however Hon’ble NCLAT was also not inclined to pass
any order in favour of the respondents and subsequently the
matter reached before the Hon’ble Supreme Court wherein upon
the undertaking of respondent No.2, respondents were granted 6
to 15 months time to complete the project. However, respondents
-- 1 of 3 --
failed to abide by the same and contempt proceedings were
initiated against respondent No.1 & 2. It is further submitted that
now respondent unexpectedly issued demand letter on
14.10.2024 in the name of applicant calling upon him to pay an
amount to the tune of Rs.9,87,889/- which is unreasonable and
arbitrarily. It is further stated that on 07.10.2025, applicant
received letter from the respondent wherein it is mentioned that
last and final opportunity is being given to deposit the above-
mentioned amount within 7 days failing which the allotment of
the above mentioned unit shall stand automatically
terminated/cancelled without any further notice. ld. Counsel
plaintiff stated that all these tactics are being adopted by the
respondent to harass the innocent buyers and urgent interim relief
is required to restrain the respondent from transferring or creating
any third party interest in the above mentioned unit.
Submissions of ld. Counsel for petitioner heard.
Record perused.
Considering the submission of ld. Counsel for
petitioner, this court is of considered opinion that petitioner shall
suffer irreparable loss in case exparte ad-interim order is not
passed. Hence, parties are directed to maintain the status quo qua
the residential unit No. T-2 0802 in ORION Galaxy at Sector 68,
Gurgaon.
Notice of the present petition be issued to the
respondents on filing of PF & RC / AD as well as through all
electronic modes returnable for 20.09.2025. Ld. Counsel is also
directed to file a copy of registered AD alongwith tracking record
-- 2 of 3 --
of summons and file a compliance affidavit on or before next
date of hearing. Copy of order be given dasti.