Pdf Text: Arbitration 481/2025.
Ramesh Kumar Aggarwal Vs. Soni Infratech Pvt. Ltd.
13.08.2025
Fresh petition u/S 9 of Arbitration and Conciliation Act received
by assignment.
It be checked and registered.
Present : Mr. Piyush Chhabra, Mr. Anand Beniwal & Ms.
Riya Srivastava, Ld. Counsels for the petitioner.
Fresh petition u/S 9 of Arbitration and Conciliation
Act is filed alongwith the application for urgent hearing. It is
submitted by ld. Counsel for petitioner that one residential unit
No. T-7 0504 in ORION Galaxy at Sector 68, Gurgaon was
bought by one Rajiv Soni who later sold the same to late father of
the applicant Mr. Chandrabhan. It is further stated that after
passing of Mr. Chandrabhan, the unit was transferred in the name
of the applicant through Will. It is further stated that respondent
No.1 is the private Limited Company operated within the Real
Estate and Infrastructure Development Sector and the respondent
No.2 to 7 are the officials of respondent No.1. It is further stated
that in the year 2010 one Rajiv Soni was induced by the
respondents to book the above mentioned unit. However, despite
receiving the substantial amount out of the total payable amount,
the respondent miserably failed to complete the same. It is further
stated that insolvency proceedings was initiated against the
respondent company and consequently Interim Resolution
Professional (IRP) was appointed vide order dated 22.11.2019
passed by Hon’ble NCLT. It is further stated that appeal was
-- 1 of 3 --
preferred against the order of NCLT however Hon’ble NCLAT
was also not inclined to pass any order in favour of the
respondents and subsequently the matter reached before the
Hon’ble Supreme Court wherein upon the undertaking of
respondent No.2, respondents were granted 6 to 15 months time
to complete the project. However, respondents failed to abide by
the same and contempt proceedings were initiated against
respondent No.1 & 2. It is further submitted that now respondent
unexpectedly issued demand letter on 14.10.2024 in the name of
applicant calling upon him to pay an amount to the tune of
Rs.30,79,706/- which is unreasonable and arbitrarily. It is further
stated that on 07.10.2025, applicant received letter from the
respondent wherein it is mentioned that last and final opportunity
is being given to deposit the above-mentioned amount within 7
days failing which the allotment of the above mentioned unit
shall stand automatically terminated/cancelled without any
further notice. ld. Counsel plaintiff stated that all these tactics
are being adopted by the respondent to harass the innocent
buyers and urgent interim relief is required to restrain the
respondent from transferring or creating any third party interest
in the above mentioned unit.
Submissions of ld. Counsel for petitioner heard.
Record perused.
Considering the submission of ld. Counsel for
petitioner, this court is of considered opinion that petitioner shall
suffer irreparable loss in case exparte ad-interim order is not
passed. Hence, parties are directed to maintain the status quo qua
the residential unit No. T-7 0504 in ORION Galaxy at Sector 68,
Gurgaon.
-- 2 of 3 --
Notice of the present petition be issued to the
respondents on filing of PF & RC / AD as well as through all
electronic modes returnable for 20.09.2025. Counsel is also
directed to file a copy of registered AD alongwith tracking record
of summons and file a compliance affidavit on or before next
date of hearing. Copy of order be given dasti.
(Meenu Kaushik)
District Judge-03
Patiala House Courts, New Delhi
13.08.2025