Order Details: COPY OF JUDICIAL PROCEEDINGS
Pdf Text: RC ARC 6/26
PURAN CHAND AND CO Vs. GODREJ and BOYCE MANUFACTURING CO LTD
23.05.2026
Present : Ld. Counsel for petitioner.(through VC)
Ld. Counsel for respondent. (through VC)
As per report of the Ahlmad, rejoinder has been filed on behalf of the
respondent on 07.03.2026. Copy already supplied to the opposite side
An application is also filed on behalf of the respondent under Section 151
CPC on 07.03.2026 alongwith the detailed affidavit under Section 25(B)(4) of the DRC
Act. It is
inter-alia prayed that the additional affidavit filed alongwith the application be
taken on record after condoning the delay and the court fees may also be taken on record.
A query was put as to the power of this court, to condone the delay in taking
the additional affidavit on record and Ld. Counsel for petitioner has clarified that she has
only filed the application with abundant caution as the petitioner has taken such technical
objections in the reply to the application seeking leave to defend.
Ld. Counsel for petitioner, at this juncture, has submitted that he shall not
refer to such technical objections and the application seeking leave to defend may be
considered on merits.
Accordingly, in view of such submissions, the application under 151 CPC
filed by the respondent is disposed off with the clarification that the delay, if any, cannot
be condoned by this court.
Arguments heard from both the sides at length on the application seeking
leave to defend.
Be adjourned for orders/clarification, if any for 12.06.2026 @ 04.00 PM.