Full Order Text
Interim Order 5 · 19 Sept 2024 · CNR DLCT030048862023
Order Details: COPY OF JUDICIAL PROCEEDINGS Pdf Text: 24 CS SCJ 1725/23 TORET ALI Vs. IRRIGATION AND FLOOD CONTROL DEPARTMENT 19.09.2024 Present: Sh. Vinay Kumar Phatak, Ld. counsel for plaintiff. Sh. Sachin Sharma, Ld. counsel for defendant alongwith clerk of defendant Sh. Subhash. Ld. counsel for the plaintiff states that he does not wish to file reply to the application U/O 8 Rule 1 CPC and will straight away address the arguments. Arguments on the application heard on behalf of the parties. Record perused. Ld. counsel for the defendant argued that the WS could not be filed within time as there was a delay in appointment of counsel by the defendant which is a government department, due to its formal procedure. It was prayed that the application be allowed. Per contra, application was opposed on behalf of the plaintiff. It was argued that the present application be dismissed. Submissions heard. Record perused. It is settled law that procedures are nothing but handmaid of justice and when technicalities are pitched against justice, it is the cause of justice which is to be given paramount importance. It is noteworthy to mention that for efficacious disposal of the suit, it is desirable that opportunity must be given to both the parties to represent their case on merits and though in the present case there is a delay in filing of WS but in the considered opinion of this court, if the same is not condoned, efficacious adjudication on merits cannot be made. -- 1 of 2 -- -2- In view of the above observation and considering the reason stated for not filing the WS in time, application U/O 8 Rule 1 CPC moved on behalf of defendant is allowed subject to cost of Rs.500/- to be paid by the defendant to the plaintiff. Replication if any, be filed on or before the next date alongwith advance copy to the opposite side. Now to come up on 19.12.2024. (KAPIL GUPTA) Civil Judge-06 (Central) Tis Hazari Courts Delhi/19.09.2024 -- 2 of 2 --