Full Order Text
Interim Order 29 · 09 Jul 2026 · CNR DLCT010049342024
Order Details: COPY OF ORDER Pdf Text: IN THE COURT OF SH. MANOJ KUMAR-I, DISTRICT JUDGE (COMMERCIAL COURT)-05, CENTRAL, TIS HAZARI COURTS, DELHI. Execution (COMM) No. 131/2024 In the matter of: M/s Janki Enterprises versus M/s Mangalmay Radhey International and others ORDER This order shall decide an application under section 151 of the Code of Civil Procedure, 1908 (CPC) made on behalf of judgment debtor No. 3 Krishan Mangal. 2. It is, inter alia, stated in the application that on 02.5.2026 the execution petition was listed before this court, however on 02.5.2026 the judgment debtor/applicant deposited 1,00,000/- by NEFT in the ₹ morning time; that the said fact was concealed by decree holder by not mentioning the same in the court; that due to fracture in the right hand of the judgment debtor he could not appear before the court when the above said execution petition was called; that counsel for the judgment debtor also did not appear before the court at that time; that in the very morning on 02.5.2026 the judgment debtor deposited 1,00,000/- by ₹ NEFT; that the total settlement was made for 33,00,000/-, and, out of ₹ Contd... -- 1 of 7 -- -2- the said amount, the judgment debtor has already paid 22,70,000/- upto ₹ 02.5.2026; that the remaining amount worth 10,30,000/- is to be paid ₹ by the judgment debtor upto October, 2026; that the judgment debtor undertake to pay the same upto October, 2026 in all respect; that the judgment debtor further undertook to pay the abovesaid amount in parts time to time upto October, 2026; that the judgment debtor undertook that he would pay the said amount in all respect upto the said period; that on 02.5.2026 the court passed the order for detention of the judgment debtor for 7 days; that there is no bad intention of the judgment debtor in any manner in making the payment of the said amount; that due to fracture, the judgment debtor could not work and he could not collect the money from the market; that the above said amount as per settlement can be paid upto October, 2026; that the judgment debtor shall pay the same within the said specific period; that the order dated 02.5.2026 is required to be recalled and the judgment debtor may be given some more time to make the payment within the specific period upto October, 2026. It is stated that the judgment debtor may be allowed to pay the entire balance amount in parts upto October, 2026 as per settlement under the abovementioned circumstances of the case and also in the interest of justice. 3. The application is contested by the decree holder by way of a written reply wherein it is stated that the present application filed Contd... -- 2 of 7 -- -3- under section 151 CPC is not maintainable in the eyes of law as the present application filed by the J.D. is false, frivolous, misconceived and has been filed only to delay the execution proceedings and avoid compliance with the lawful orders of this court; that the allegation that the D.H. concealed the deposit of 1,00,000/- from this court is false ₹ and baseless; that even if the J.D. had initiated the alleged NEFT transaction in the morning of 02.5.2026, the amount is not credited instantaneously in every case; that an NEFT transaction is processed through the banking system and may take some time before the amount is actually credited to the beneficiary’s account; that unless and until the amount was reflected in the account of the decree holder, the D.H. had no knowledge or confirmation of the alleged deposit and, therefore, there was no question of concealing the said fact from this court; that the J.D. has repeatedly failed to honour the terms of the settlement and has committed continuous defaults in payment; that the plea regarding fracture in his hand is an afterthought and does not justify his non- appearance or non-compliance with the settlement; that the J.D. has deliberately concealed the material fact that he has repeatedly violated the terms of the settlement arrived at between the parties; that initially, the matter was settled before the Mediation Centre, wherein the J.D. had undertaken to pay a sum of 3,00,000/- per month; that the J.D. failed to ₹ honour the said settlement and committed repeated defaults; that thereafter, another arrangement was recorded before this court, whereby Contd... -- 3 of 7 -- -4- the J.D. undertook to pay 1,00,000/- per month; that even the said ₹ undertaking was not complied with by the J.D., who again defaulted in making the payments as agreed; that having repeatedly breached the terms of the earlier settlements and undertakings, the J.D. cannot now seek any equitable relief or rely upon yet another alleged settlement or undertaking for payment of the balance amount by October, 2026; that the conduct of the J.D. clearly demonstrates that his assurances are neither bona fide nor reliable and have been made only to delay the execution proceedings; that in view of the repeated breaches committed by the J.D., the alleged settlement has lost its sanctity and is no longer enforceable against the decree holder; that the decree holder is entitled to execute the decree for the entire decretal amount along with interest; that the J.D. cannot be permitted to take advantage of his own breaches and seek enforcement of a settlement which he himself has failed to perform; that having repeatedly violated the terms of the compromise, the J.D. has rendered the settlement ineffective and unenforceable; that the J.D. has forfeited any benefit arising out of the said compromise; that the total decretal amount, as on the date of filing of the execution petition i.e. 03.4.2024 was 52,07,498/- (principal decretal amount to the tune of ₹ 30,00,000/-, interest to the tune of 21,75,782/- and the court fee to the ₹ ₹ tune of 31,716/-); that the aforesaid amount is subject to adjustment of ₹ the payments, actually received by the decree holder; that the repeated defaults committed by the J.D. disentitle him from claiming the benefit Contd... -- 4 of 7 -- -5- of the conditional settlement, and the decree holder is legally entitled to execute the decree for the entire decretal amount, subject to such adjustment; that the contention of the J.D. that only 10,30,000/- ₹ remains payable is wholly false, misconceived and liable to be rejected; that order dated 02.05.2026 passed by the court does not suffer from any illegality or infirmity. It is stated that the application under section 151 CPC filed by the J.D. be dismissed and the execution proceedings be continued in accordance with law. 4. I have heard counsel for the parties and have gone through the material on record carefully. 5. Having drawn the attention of the court on the contents of the application it is submitted by counsel for the judgment debtors that after passing of the decree, during the execution proceedings the matter was referred to the Mediation Centre wherein a settlement was effected between the parties. It is further submitted by counsel for the judgment debtors that after the settlement the judgment debtors regularly made the payment to the decree holder, but due to some unavoidable circumstances, on some occasions, they could not make the payment as per the settlement on time and have defaulted in making some payments. It is further submitted by counsel for the judgment debtors that the judgment debtors are ready to make the payment by the month of October 2026, therefore, as per the settlement effected between the Contd... -- 5 of 7 -- -6- parties before the Delhi Mediation Centre the judgment debtors may be permitted to make the payment in installments as agreed to between the parties before the Delhi Mediation Centre. 6. Per contra, it is submitted by counsel for the decree holder that the judgment debtors did not comply with the terms of the settlement entered into between the parties before the Delhi Mediation Centre, therefore, now they cannot take advantage of the said settlement. It is further submitted by counsel for the decree holder that the judgment debtors so far have made payment of 24,00,000/- approximately, and ₹ they are still liable to pay 28,00,000/- under the decree passed against ₹ them by this court. It is further submitted by counsel for the decree holder that the application is misconceived and the same be dismissed. 7. I have given thoughtful consideration to the submissions made on behalf of the parties. 8. As per the record of the proceedings, the decree holder/ plaintiff instituted a suit CS (COMM) No. 2891/2021 against the judgment debtors/defendants, wherein, after trial, by judgment and decree dated 11.10.2023, passed by the learned predecessor, the claim of the decree holder was allowed in terms that the decree holder was found entitled to 30,00,000/- against the judgment debtors with interest at the ₹ rate of 12% per annum from 18.3.2018. Since the judgment debtors did not satisfied the decree dated 11.10.2023, therefore, the decree holder made the present application for execution of the said decree. During the Contd... -- 6 of 7 -- -7- pendency of the execution proceedings, at the request of the parties, the matter was referred to the Delhi Mediation Centre for mediation, where, on 27.7.2024, a settlement was effected between the parties whereunder the judgment debtors/ defendants agreed to pay sum of 33,00,000/- in ₹ eleven equal monthly installments of 3,00,000/- each on or before ₹ every 10th day of English calendar month starting from August, 2024. As per the said settlement the parties would be governed by the terms and conditions of the settlement and in case the judgment debtors/defendants did not comply, the decree holder would be at liberty to take appropriate action as per law. 9. Admittedly, the judgment debtors have not complied with the terms and conditions of the settlement effected between the parties before the Delhi Mediation Centre, and therefore, the judgment debtors, now, cannot insist that the decree holder should comply with the terms of the settlement and should receive money from them in installments as per the said settlement. Permitting such arrangement shall tantamount to execution of the decree as per the wish and desire of the judgment debtors. Since the judgment debtors have not complied with the terms of the said settlement effected between the parties before the Delhi Mediation Centre on 27.7.2024, therefore, the present application is misconceived and the same is dismissed. Pronounced in the open court on the 09th day of July, 2026 (MANOJ KUMAR-I) District Judge (Commercial Court)-05 Central District: Tis Hazari: Delhi -- 7 of 7 --